M27 Southampton junction 8

We're making improvements to the M27 junction 8 and Windhover roundabout.

Start date Autumn 2023
End date TBC
Cost £25 - £50 million

Latest updates

  • 22 June 2023

    Public Inquiry outcome

    The Secretary of State has not approved our application for Compulsory Purchase Order and Side Road Order powers which would allow us to make improvements to the M27 Junction 8 near Southampton.

    We accept the Secretary of State’s decision and will now take some time to review the detailed contents and advice within the Inspector’s Report to determine how best to proceed.

    We understand the challenges at M27 Junction 8 and Windhover have not gone away and we remain committed to working with our partners to support our shared objectives for the local area, which are to improve safety and reduce congestion.

     

Project information

Overview

Research has shown that the M27 junction 8 has unfortunately had a significant number of casualties, particularly between 2009 and 2011.

Poor air quality associated with vehicle emissions is currently an issue within the local area. The local authorities are keen to make improvements to encourage more sustainable modes of transport such as walking, cycling or public transport in an effort to improve air quality and health.

Congestion at Windhover roundabout is currently caused by a combination of localised peak time traffic (7am to 10am and 4pm to 7pm) and rat-running to avoid M27 junction 8 tailbacks.

The scheme improvements will help alleviate traffic congestion which will benefit the community in terms of better air quality for local residents and support the economy by providing improved journey times for local businesses using the route. The improvements will lead to a reduction in the number of casualties.

The aims of this scheme are to:

  • support economic growth – contributing to sustainable economic growth by supporting employment and local residential development opportunities
  • improve connectivity and reduce journey times around M27 junction 8 and Windhover Roundabout
  • provide a safe and serviceable network – improving the safety record at M27 junction 8 and Windhover Roundabout (60 year look ahead assessment period)
  • provide a more free-flowing and reliable network – reducing congestion around the M27 junction 8 and Windhover Roundabout and improve journey time reliability and connectivity between east and west of the M27 junction 8 – Windhover Roundabout
  • provide a safe, accessible and integrated network – delivering capacity enhancements to the M27 junction 8 and Windhover Roundabout, while supporting the safe, accessible use of active travel modes for pedestrians and cyclists
  • provide an improved environment – seeking to prevent the worsening of air quality by reducing congestion and journey times along the M27 junction 8 and Windhover Roundabout and aiming to mitigate noise impact

Documents

Stage 2 reports

Environmental Assessment Report

Stage 3 reports

Notice of Determination
Environmental Assessment Report
Environmental Deliverables Index
Environmental Assessment Report - Construction Dust Assessment
Environmental Assessment Report - Air Quality Affected Road Network And Receptors
Environmental Assessment Report - Air Quality Monitoring Data And Baseline
Modelled Change In No2 Between The Dm And Ds 2021 For Human Receptor
Environmental Assessment Report - Modelled Change In No2 Between The Dm And Ds 2021 For Ecological Receptors
Environmental Assessment Report Statutory Designated Sites
Environmental Assessment Report - Statutory Designated Sites
Environmental Assessment Report - Non-Statutory Designated Sites

Environmental Constraints Plan
Environmental Assessment Report - Visual Receptors
Environmental Assessment Report - Landscape Constraints
Environmental Assessment Report - Landscape Character
Environmental Assessment Report - Zone Of Theoretical Visability
Environmental Assessment Report - Environmental Masterplan - Sheet 1 Of 2
Environmental Assessment Report - Environmental Masterplan - Sheet 2 Of 2
Environmental Assessment Report - Winter Views 1 And 2 - Sheet 1 Of 6
Environmental Assessment Report - Winter Views 3 And 4 - Sheet 2 Of 6
Environmental Assessment Report - Winter Views 5 And 6 - Sheet 3 Of 6
Environmental Assessment Report - Winter Views 7 And 8 - Sheet 4 Of 6
Environmental Assessment Report - Winter Views 9 And 10 - Sheet 5 Of 6
Environmental Assessment Report - Winter Views 11 And 12 -Sheet 6 Of 6

Environmental Assessment Report - Summer Views 1 And 2 - Sheet 1 Of 6
Environmental Assessment Report - Summer Views 3 And 4 - Sheet 2 Of 6
Environmental Assessment Report - Summer Views 5 And 6 - Sheet 3 Of 6
Environmental Assessment Report - Summer Views 7 And 8 - Sheet 4 Of 6
Environmental Assessment Report - Summer Views 9 And 10 - Sheet 5 Of 6
Environmental Assessment Report - Summer Views 11 And 12 - Sheet 6 Of 6
Environmental Assessment Report - Study Areas For Noise And Vibration
Environmental Assessment Report - Construction Noise Effects
Environmental Assessment Report - Operational Noise Effects
Windhover Roundabout Temporary Traffic Management Phase 1
Windhover Roundabout Temporary Traffic Management Phase 2
Windhover Roundabout Temporary Traffic Management Phase 3a & C
Windhover Roundabout Temporary Traffic Management Phase 3b
Windhover Roundabout Temporary Traffic Management Phase 4a
Windhover Roundabout Temporary Traffic Management Phase 4b
Windhover Roundabout Temporary Traffic Management Phase 5a
Windhover Roundabout Temporary Traffic Management Phase 5b

Junction 8 Temporary Traffic Management Phase 1
Junction 8 Temporary Traffic Management Phase 2
Junction 8 Temporary Traffic Management Phase 3
Junction 8 Temporary Traffic Management Phase 4


Windhover Roundabout Proposed Diversion Phase 6a
Windhover Roundabout Proposed Diversion Phase 6b
Windhover Roundabout Proposed Diversion Phase 6c
Windhover Roundabout Proposed Diversion Phase 6d
Windhover Roundabout Proposed Diversion Phase 6e
Windhover Roundabout Proposed Diversion Phase 6f
Junction 8 Proposed Diversion Phase 5a
Junction 8 Proposed Diversion Phase 5b
Junction 8 Proposed Diversion Phase 5c

General Arrangement Plan Sheet 1 Of 5
General Arrangement Plan Sheet 2 Of 5
General Arrangement Plan Sheet 3 Of 5
General Arrangement Plan Sheet 4 Of 5
General Arrangement Plan Sheet 5 Of 5
Construction Methodology And Phasing Report - Appendix E Construction Programme
Environmental Assessment Sensitivity Test Technical Note
Flood Compensation Areas Technical Note 
Biodiversity Baseline Report
Cultural Heritage Report
Arboricultural Report
Flood Risk Assessment

Traffic information

Information about scheduled roadworks and events on our motorways and major roads.

Contact us

info@nationalhighways.co.uk

Sign up for updates!

Keep up to date with what's happening on this scheme by signing up to our updates.

Feedback