M27 junction 12 Hilsea Interchange IBM bridge repairs

We need to carry out essential repairs to two bridges near the M27 junction 12 Hilsea Interchange in Hampshire.

Start date 5 June 2025
End date End of November 2025
Cost Approximately £5 million

Latest updates

  • 18 July 2025

    First phase complete

    We've now completed the first phase of our works ahead of programme. The lane closures have been removed, while other works not requiring lane closures, continue underneath. 

    Our next phase of closures are:

    • Eastbound: Monday 4 August – Thursday 7 August. 9pm – 6am nightly
    • Westbound: Monday 18 August – Thursday 21 August. 9pm – 6am nightly

  • 15 July 2025

    Overnight closures planned for August

    We're still working overnight until Monday 4 August (lane closures).

    From Monday 18 to 27 August (9pm-6am) we'll have overnight weeknight closures.

  • 15 May 2025

    Essential work starts soon

    Essential repairs start soon on two bridges near the M27 Junction 12 Hilsea Interchange in Hampshire.

    Known locally as the IBM bridges, one carries the M27 carriageway eastbound and the other westbound, near the Portsbridge Roundabout.

    The work will include replacing both bridges’ expansion joints: these allow for the expansion / contraction of bridge decks, caused by temperature variations and traffic movement. 

    We'll also:

    • replace kerb drainage and upgrade the drainage systems
    • re-waterproof and resurface the bridge decks
    • repair concrete underneath both bridges 

    For safety, we need lane closures throughout June, July and early August. There'll be

    • a 24/7 lane closure of the M275 northbound to where it joins the M27 eastbound, starting 22 June and continuing for three weeks
    • lane closures from 8pm Thursday night through to 6am Monday morning on the M27 westbound

    We'll also need some overnight, full carriageway closures in August. We'll do this in one direction at a time to limit disruption to traffic as much as possible. 

    In September to the end of November, we'll need some full weekend closures. We'll do this in one direction at a time to limit disruption to traffic as much as possible. We'll update this web page with full dates/details once they're confirmed.

Project information

Overview

We need to: replace kerb drainage and upgrade the drainage systems; re-waterproof and resurface the bridge decks and repair concrete underneath both bridges.

The new expansion joints and re-waterproofing will substantially improve the longevity of the two bridges.

Documents

Traffic information

Information about scheduled roadworks and events on our motorways and major roads.

Contact us

info@nationalhighways.co.uk

Sign up for updates!

Keep up to date with what's happening on this scheme by signing up to our updates.

Feedback