Check current delays, incidents and closures.
See planned and ongoing road improvement work.
Guidance and services for professional drivers.
Support, advice and services if you're disabled.
How we support people travelling as pedestrians, by bike or by horse.
Key rules and signs for using our roads
Practical tips for safer, smoother journeys
Our investment in local communities
How we restore and enhance the environment
How we create the space for ideas and innovation to thrive across industry and academia
How we manage and improve our roads
What we're accountable for as a road authority.
The people and organisations we work with to keep the network safe, moving and improving
See our press releases and statements and contact our Press Office.
How to work with us as a supplier
Jobs, career paths and life working with us
Links to the pictures, illustrations and tables used in this evaluation.
Scheme location
Forecast and observed change in traffic volume (three years after opening)
Counterfactual comparison for journey times – northbound
Counterfactual comparison for journey times – southbound
Journey time reliability – northbound
Journey time reliability – southbound
Number of personal injury collisions before the project, during construction, and after the project opened.
Failed open grassland planting along the A500 northbound (adjacent to new shared cycle / footpath)
Successful open grassland planting along the A500 northbound (adjacent to new shared cycle / footpath)
Scrub planting along the A500 shared cycle / footpath
New shared cycle / footpath adjacent to the A500
Public Right of Way 83: existing facility under the A500