Works programme
The list below shows HRE major schemes identified for works from November 2024 to April 2025, covering England, Scotland and Wales.

It makes up a small proportion of our work to maintain safety on and around our structures. The list gives an overview of our larger schemes, which include repairs, refurbishment, proposed infill* or demolition.
In addition to the schemes listed in this programme, we deliver up to 500 minor works schemes every year. Work includes strengthening, vegetation removal and repairs among other things.
Our programme of major works will develop over time and the information published here is subject to change. We will publish an updated programme regularly.
Further information
ELR | Name | Region | Location | Description of works | Provisional start of works date |
---|---|---|---|---|---|
AGB/3 | Luffness Mains | East Lothian | Scotland | Repairs | In progress |
HLP/5S | Station Road | Warwickshire | England | Refurbishments and repairs | In progress |
RLB/1 | Riddings Viaduct | Dumfries and Galloway | Scotland | Structural repairs | In progress |
CNB3/72A | Millers Dale Viaduct | Derbyshire | England | Repairs and waterproofing | In progress |
BMZ/6A | Glynogwy Sidebridge | Bridgend | Wales | Scour repairs | In progress |
SUX/4A | Bromshall Tunnel | Staffordshire | England | Repairs | Summer 2025 |
KEH/2 | River Isle | Kettering | England | Scour repairs | Summer 2025 |
DAS1/5 | Low Ashyard Hurlford | East Ayrshire | Scotland | Installation of support structure | Autumn 2025 |