M62 Ouse Bridge

Following an eastbound bridge joint failure in the spring, a contraflow is now in operation on Ouse Bridge

Start date April 2022
End date 2024
Cost TBC

Latest updates

  • 22 October 2024

    Changes to speed limits on Ouse Bridge

    As of Monday 21 October 2024, the eastbound carriageway of the M62 Ouse Bridge, between junctions 36 and 37, was changed to 70mph with the hard shoulder, lane 1 and lane 2 reopened.

    The westbound carriageway presently has a speed limit of 50mph; however, this too is expected to be running at 70mph from first thing on Wednesday 23 October. There will still be a lane 3 and hard shoulder closure in operation on the westbound carriageway.

    We're working hard to reopen lane 3 in both directions and this should be the case for the morning of Monday 28 October. The westbound hard shoulder will remain closed. Additional overnight lane closures can be expected for finishing works.

  • 17 October 2024

    Changes to traffic management and speed limits as repairs near completion

    The contraflow arrangement for westbound traffic on the M62 Ouse Bridge has been lifted as of Tuesday 15 October. With it, the speed limit on that section has been increased from 30mph to 50mph. Two lanes are open on the westbound carriageway, with lane 3 and the hard shoulder remaining closed.

    The eastbound carriageway will continue to run with narrow lanes, with the speed limit remaining at 30mph while we continue to remove traffic management. 

    We currently anticipate the eastbound carriageway to be running with two standard width lanes at a 50mph speed limit by the middle of next week, subject to weather conditions, with the hard shoulder and lane 3 remaining closed.

    Once this has taken place and the last sections of the traffic management are removed, we shall remove the 50mph restrictions on both carriageways and return to three lanes of traffic at the national speed limit in each direction. We currently expect this to take place by the end of next week (ending 27 October).

    Both hard shoulders will remain closed at this point to complete additional works at the outer verges and these closures will remain in place until early December. Overnight lane closures during this period will also be undertaken to enable these finalising works.

    We'll share further updates on this page, and on our social media feeds @HighwaysYORKS and National Highways: Yorkshire Facebook page in due course. We'd like to thank everyone once again for their patience.

  • 29 July 2024

    We're entering the final phase of our work

    We're preparing to switch traffic between junctions 36 (Goole) and 37 (Howden), into a new contraflow. Vehicles will use the eastbound carriageway as work begins on the westbound carriageway.

    We'll also close a single lane on the westbound for traffic joining from the junction 37 entry slip.

    To do this, we'll need to close the M62 eastbound between junctions 36 and 37 (overnight between 8pm and 9am) in early August. We'll follow this with closures on the westbound carriageway, between junctions 38 (North Cave) and 36.

    Please remember that closure details can change at short notice. For the most up-to-date information, please visit our daily closures page.

    We expect to complete our works in mid-Autumn 2024.

  • 11 March 2024

    Moving to the next phase of works

    Work on the bridge is progressing well and we've successfully completed repairing bridge joints in the hard shoulder and lane 1.

    We're moving on to the next phase of work in lanes.

    We'll move traffic over to use the hard shoulder and lane 1. This will allow us to start hydro demolition and concrete repairs of the joints in lanes 2 and 3.

    One lane eastbound lane will still be running in lane 3 of the westbound carriageway.

    After we complete bridge joints on the eastbound side of the bridge in mid-spring, we'll switch work to the westbound carriageway.

    We will have to use carriageway closures:

    • to work on bridge joints we can't reach with lane closures
    • to performa essential maintenance in the contraflow area

    Remember that closures can change at short notice. Check the latest information on our daily closures page.

    We're reminding you to plan your journeys, allow extra time for travelling and check traffic conditions before setting off.

  • 24 November 2023

    Our progress at November 2024

    We're using hydro demolition to remove damaged concrete and prepare for the new joints in the hard shoulder and lane 1. 

    We've already started pouring the new concrete section ready to install the new joints.  We expect these sections to be complete early in the new year.

    We have developed our programme and will be replacing all 8 joints on the bridge as part of this scheme. This will reduce the need for further work in the near future.

    What happens next 

    This is our indicative programme of the work we'll be carrying out between now and completion.

    These dates may be subject to change depending on bad weather or any unexpected delays. 

    • Eastbound hard shoulder and lane one work to be complete by mid-January 2024
    • traffic moved to allow work on Lane 2 and 3 eastbound January 2024
    • lane 2 and 3 eastbound to be complete by the end of February 2024
    • traffic moved to allow work on Lane 3 east and westbound, end of February 2024
    • all work completed on the eastbound carriageway by mid-May 2024
    • mid-May, work to switch to westbound carriageway and to be complete by end of Summer 2024

    We will provide regular updates as work progresses.

Project information

Overview

Routine investigations identified a partial failure of a joint on the eastbound carriageway.

Extensive investigations are under way to establish what repairs are required, which will then allow us to develop a detailed design of the works and a work programme.

These processes take time and we appreciate the inconvenience this may be causing to road users. Safety is paramount, not only for road users but also to all of our engineers who are working on the scheme and lane closures will have to remain in place until the works are complete.

As the programme progresses we'll continue to provide regular updates through this page and our social media.

The M62 is a vital link to Hull and the rest of the county and the Ouse Bridge is vital in maintaining this link.

This project will repair the joint and we will re-open the lanes to all traffic as soon as possible, we will continue to provide updates as the project develops.

Safety of all road users and our workers is essential and this is why we need to install the contraflow. 

Documents

Traffic information

Information about scheduled roadworks and events on our motorways and major roads.

Sign up for updates!

Keep up to date with what's happening on this scheme by signing up to our updates.

Feedback