A1 Wentbridge Viaduct and Wentedge Road Bridge

Following several reactive repairs, we plan to carry out inspections and resurfacing on Wentbridge Viaduct and a pier replacement on Wentedge Road Bridge. This work is substantial and is likely to cause disruption to customers travelling on the A1.

Start date February 2023
End date Summer 2024
Cost £9.4m

Latest updates

  • 17 April 2024

    A1 Wentbridge Viaduct and Wentedge Road Bridge April update

    Work continues on the two bridges following the contraflow switch in March, which allowed us to start on the northbound carriageway of Wentbridge Viaduct. 

    Our work continues to be delivered using a mix of day and night shifts by a number of specialist contractors. There will be periods when the site is less busy while the results of inspections are considered and the design work for the solutions are progressing. 

    The northbound bridge deck is now exposed to allow for detailed inspections of the concrete, with the removal of surfacing and waterproofing layers over the last few weeks. 

    Roadworkers drilling out concrete during road repairs.

    Following initial inspections, we're progressing work on the concrete 'deck ends' of each section of the bridge after uncovering signs of age related deterioration. Damaged areas are being removed using hand machinery rather than large plant machinery, to protect the post tensioned cables within the concrete.  Post tensioning systems are an integral part of the bridge, providing structural integrity. 

    Once all the inspections are completed we will provide another update about our findings. 

    At the same time, using those same closures last month, the following work was completed on other sections of the A1T nearby. 

    • 3.5 lane kilometres (3,260 Tonnes) of surfacing materials laid. 

    • 10,060 m. of road markings renewed 

    • 1,390 road studs replaced 

    • 1 traffic sign replaced 
    • 3 technology and communication sites renewed
    • 1 weather station replaced 
    • Litter picking
    • Grass cutting 
    • Drainage cleaning
    • Road sweeping 

    Wentedge Bridge - inspections continue and design work on the central pier is ongoing. 

    Our advice for drivers remains the same; please stay on the A1 - the route is open under contraflow and delays at peak times are up to 40 minutes on average.  Alternatively, drivers can use the M62 and M18 as an alternative route. 

    Local villages have a number of weight, height and environmental restrictions and these are being monitored and enforced by the Police.  We are also supporting speed awareness by deploying a Safety Camera Vehicle in across several locations and this data is share with the Police for enforcement. 

    Thank you to drivers, residents and businesses for your continued patience during this complex repair programme. 

  • 22 February 2024

    Update - full list of closures for February and March

    We've previously shared information regarding closures taking place for the next phase of work on Wentbridge Viaduct. We are now able to share the full programme although these dates are subject to change in the event of poor weather conditions. 

    A1 closures will take place overnight from 8pm until 6am and fully signed diversion routes will be in place.  

    • Thursday 22nd Feb – southbound full closure
    • Friday 23rd Feb – northbound full closure
    • Saturday 24th Feb – northbound full closure
    • Sunday 25th Feb – northbound full closure 
    • Monday 26th Feb – southbound full closure
    • Tuesday 27th Feb – southbound full closure
    • Wednesday 28th Feb – southbound full closure 
    • Thursday 29th Feb – northbound full closure 
    • Fri 1st March – northbound full closure 
    • Sat 2nd March – northbound full closure 
    • Sun 3rd March – northbound full closure 
    • Monday 4th March – northbound full closure 
    • Tuesday 5th March – northbound full closure 
    • Wednesday 6th March – northbound full closure 
    • Thursday 7th March – northbound full closure 
    • Friday 8th March – northbound full closure 
    • Wednesday 20th March – northbound full closure 

    Drivers are recommended to stay on the motorway network where possible using the M62 and M18 for both northbound and southbound journeys. Please do not follow Satnavs as they may not consider restrictions on local routes. 

    • Southbound traffic to use the M62 and M18
    • Northbound diversion - traffic on A1 up to Wadworth (junction 35) - leave junction 35 onto M18 and M62 to Ferrybridge Interchange.
    • Northbound high-sided vehicles, traffic north of Wadworth (junction 35) - leave A1 at Barnsdale Bar onto A6201 and onto A628 re-joining A1 from the A645 via Ferrybridge Interchange. The Environmental Weight Restriction for HGVs (Heavy Goods Vehicles) on A628 Ackworth has been revoked only during overnight closures of the A1. This is due to height restrictions on an alternate route.
    • Northbound diversion, traffic north of Wadworth (junction 35) - leave A1 at Barnsdale Bar onto A639, re-joining A1 from the A645 via Ferrybridge Interchange. There are height restrictions on this route

    Map of the A1 showing diversion routes for Wentbridge Viaduct roadworks.

    During overnight closures, for those residents who live directly on the A1, previous escort arrangements will be back in place.

    We apologise for any inconvenience this essential maintenance causes and appreciate your continued patience while we progress the work.

  • 16 February 2024

    A1 Wentbridge Viaduct and Wentedge Road Bridge February update

    Answers to queries about the project so far, timescales and approach can be found in our Frequently Asked Questions section.

    Traffic switch to allow work to start on the northbound carriageway. 

    We want to remind drivers and residents of overnight closures on the A1 starting next week as a major scheme of work on Wentbridge Viaduct takes its next steps forward. Work to waterproof and resurface the southbound carriageway is near completion.

    Road workers laying tarmac

    The closures will be in place to move the contraflow currently in place between Barnsdale Bar and Ferrybridge, enabling essential work to switch from the A1 southbound to northbound. 

    • The closures will be in place each night, between 8pm and 6am, from 22 February until 8 March.  Closures will be in both directions, but not at the same time. During the day, the A1 will be open under contraflow.  

    • To reduce the impact of the work on road users and residents, National Highways has brought forward further maintenance and repair work to take place between 1 and 8 March. This is in addition to previously advertised closures up to 1 March.  

    The work will be carried out at the same time as the traffic switch-over.  The additional overnight closures will allow for resurfacing work, road marking, new signage, an upgraded weather station, drainage cleaning, vegetation clearance and litter picking between Barnsdale Bar and the viaduct.  

    • A single overnight closure is also due in place on 20 March.  
    • All work is subject to weather conditions. 

    We need to close the A1 between Barnsdale Bar and Ferrybridge Interchange in both directions, but not at the same time. We will work between 8pm and 6am each night. During the daytime, the A1 will be open under contraflow or lane closures. 

    Drivers are recommended to stay on the motorway network where possible using the M62 and M18 for both northbound and southbound journeys.

    • Southbound traffic to use the M62 and M18
    • Northbound diversion - traffic on A1 up to Wadworth (junction 35) - leave junction 35 onto M18 and M62 to Ferrybridge Interchange.
    • Northbound high-sided vehicles, traffic north of Wadworth (junction 35) - leave A1 at Barnsdale Bar onto A6201 and onto A628 re-joining A1 from the A645 via Ferrybridge Interchange. The Environmental Weight Restriction for HGVs (Heavy Goods Vehicles) on A628 Ackworth has been revoked during overnight closures
      of the A1. This is due to height restrictions on an alternate route.
    • Northbound diversion, traffic north of Wadworth (junction 35) - leave A1 at Barnsdale Bar onto A639, re-joining A1 from the A645 via Ferrybridge Interchange. There are height restrictions on this route.

    During the overnight closures, for those residents who live directly on the A1, previous escort arrangements will be back in place.


    We apologise for any inconvenience this essential maintenance causes and appreciate your continued patience while we progress the work.

  • 05 January 2024

    A1 Wentbridge Viaduct and Wentedge Road Bridge January update

    We want to provide detailed information and appreciate you taking the time to read this and the Frequently Asked Questions update. This information has also been posted to residents by mail. 

    Wentbridge Viaduct Our aim was to renew the waterproofing and surfacing on the bridge, as well as undertaking detailed testing of the structure to assure its long-term service. These tests could only be undertaken after the existing surfacing and waterproofing was removed.

    Several issues were identified during inspections. These were degraded and damaged sections of reinforced concrete, failed manhole cover plates, damage to the maintenance walkway anchor points (under the bridge), and defects to the safety barrier foundations. 

    These repairs are now complete, and we’ve started the waterproofing and resurfacing on the southbound carriageway. Once the resurfacing is complete, we’ll switch the contraflow over before starting work on the northbound carriageway.

    We have learnt a great deal from this earlier work and are not expecting the same level of issues on the northbound section of the viaduct. However, if we do uncover similar levels of damage, we have design solutions ready following lessons learnt from the southbound carriageway. We will know more once we have removed the road surface layers and started inspections.

    Wentedge Bridge Our original project was to replace the central pier (‘leg’), joints and waterproofing on this bridge, which sits over the A1, south of Wentbridge Viaduct. We planned to carry out this work at the same time as the viaduct, to reduce the impact on our customers.

    We have identified and carried out a number of repairs to the concrete abutments (‘bridge ends’) and are in the process of completing other concrete work on the structure.

    When will this be completed?

    We plan to fully reopen the A1 by the end of summer 2024. This timescale allows us to complete the concrete work on Wentedge Bridge and the A1 northbound Wentbridge Viaduct.

    Although we are progressing concrete repairs and are still working on design solutions, we have taken the decision not to continue with the major repair work on Wentedge Bridge at this time. We will continue to design the pier replacement but will return to carry out this work during summer 2026. This will allow us to reopen the A1 after we complete work on the A1 northbound viaduct, to minimise further impact on customers.

    What happens next – traffic switch to allow work to start on the northbound carriageway. 

    We need to change the contraflow so we can switch from southbound working to northbound.  We plan to carry this out from Thursday 22 February until Friday 1 March 2024, subject to the weather conditions.  

    We need to close the A1 between Barnsdale Bar and Ferrybridge Interchange in both directions, but not at the same time. We will confirm which direction at a later date. We will work between 8pm and 6am each night. During the daytime the A1 will be open under contraflow or lane closures. 

    Drivers are recommended to stay on the motorway network where possible using the M62 and M18 for both northbound and southbound journeys.

    • Southbound traffic to use the M62 and M18
    • Northbound diversion - traffic on A1 up to Wadworth (junction 35) - leave junction 35 onto M18 and M62 to Ferrybridge Interchange.
    • Northbound high-sided vehicles, traffic north of Wadworth (junction 35) - leave A1 at Barnsdale Bar onto A6201 and onto A628 re-joining A1 from the A645 via Ferrybridge Interchange. The Environmental Weight Restriction for HGVs (Heavy Goods Vehicles) on A628 Ackworth has been revoked during overnight closures
      of the A1. This is due to height restrictions on an alternate route.
    • Northbound diversion, traffic north of Wadworth (junction 35) - leave A1 at Barnsdale Bar onto A639, re-joining A1 from the A645 via Ferrybridge Interchange. There are height restrictions on this route.

    During the overnight closures, for those residents who live directly on the A1, previous escort arrangements will be back in place.

    Get in touch.
    We apologise for any inconvenience this essential maintenance causes and appreciate your continued patience while we progress the work.

    You can keep up to date with our work on this page or you can find us on Facebook – National Highways Yorkshire.

    If you would like to discuss this scheme, you can find details of our next public information event in February, below. You can also contact National Highways 0300 123 5000 or email info@nationalhighways.co.uk

  • 04 January 2024

    Public Information Event 2024

    For the latest update on the A1 Wentbridge scheme, please read the update published on this page.

    We are hosting a second public information event, before the contraflow switch takes place, at Darrington Golf Club. You are welcome to attend to ask questions or speak with the Project Team directly.

    Place: Darrington Golf Club, Havercroft Lane, Darrington, Pontefract WF8 3BP
    Time: 10am.
    Date: Saturday 10 February 2024

    The session is expected to last around two hours, please arrive for 9.45. The venue is fully accessible and free parking is available.

    If you are unable to attend, we have an updated ‘frequently asked questions’ update for your information in the overview section below. These are questions put to us recently by residents and drivers, online and in person.

  • 15 December 2023

    A1 Wentbridge Viaduct urgent repair

    We need to close the A1 between Barnsdale Bar and Ferrybridge Interchange overnight to carry out additional repairs to gullies.  This is due to extra wear and tear on areas not normally open to traffic in the contraflow. 

    • Northbound on Saturday 16 December between 8pm and 6am. 

    Diversions

    Drivers are advised to stay on the motorway network where possible using the M62 and M18 for both northbound and southbound journeys. 

    • Northbound diversion - traffic on A1 up to Wadworth (junction 35) - leave junction 35 onto M18 and M62 to Ferrybridge Interchange.
    • Northbound high-sided vehicles, traffic north of Wadworth (junction 35) - leave A1 at Barnsdale Bar onto A6201 and onto A628 re-joining A1 from the A645 via Ferrybridge Interchange. The Environmental Weight Restriction for HGVs on A628 Ackworth has been revoked during overnight closures of the A1. This is due to height restrictions on alternate route. 
    • Northbound diversion, traffic north of Wadworth (junction 35) - leave A1 at Barnsdale Bar onto A639, re-joining A1 from the A645 via Ferrybridge Interchange. There are height restrictions on this route

     Thank you for your patience while this work is completed. 

  • 16 November 2023

    Emergency repairs - notice of overnight closures

    We are planning to close the A1 between Barnsdale Bar and Ferrybridge Interchange overnight to carry out urgent repairs to gullies. 

    • Northbound on Saturday 18 November between 8pm and 6am. 
    • Southbound on Sunday 19 November between 8pm and 6am.

    Diversions 

    Drivers are advised to stay on the motorway network where possible using the M62 and M18 for both northbound and southbound journeys. 

    • Northbound diversion - traffic on A1 up to Wadworth (junction 35) - leave junction 35 onto M18 and M62 to Ferrybridge Interchange.
    • Northbound high-sided vehicles, traffic north of Wadworth (junction 35) - leave A1 at Barnsdale Bar onto A6201 and onto A628 re-joining A1 from the A645 via Ferrybridge Interchange. The Environmental Weight Restriction for HGVs on A628 Ackworth has been revoked during overnight closures of the A1. This is due to height restrictions on alternate route. 
    • Northbound diversion, traffic north of Wadworth (junction 35) - leave A1 at Barnsdale Bar onto A639, re-joining A1 from the A645 via Ferrybridge Interchange. There are height restrictions on this route. 
    • Southbound traffic use the M62 and M18

     

    We apologise in advance for the late notification as these are unplanned repairs and thank you for your continued patience. 

    We will soon provide a wider project update once these repairs are completed and will publish that information here and on social media. 

  • 26 September 2023

    A1 Wentbridge Viaduct and Wentedge Road Bridge September update

    Our work on A1 Wentbridge Viaduct continues, working under contraflow, which allows for continued access for drivers.

    Two road engineers working on the bridge deck at Wentbridge Viaduct

    We continue to work on concrete repairs following issues uncovered during the summer and design solutions for exposed areas of reinforcement, failed manhole cover plates, damage to the maintenance walkway anchor points (under the bridge), and defects to the safety barrier are well underway.

    We are working on site using a mix of daytime and evening shifts and where resources are available, at the weekends. There may be times when there is less activity on the bridge as we carry out work behind the scenes and below the deck.

    The next set of closures are planned for December, we will provide advance notice of these once the current phase of concrete repairs are completed.

    Thank you for your patience while we continue to progress with these major repairs on both structures. 

  • 31 July 2023

    A1 Wentbridge Viaduct and Wentedge Road Bridge July update

    We've been onsite for six months and want to provide an update about our work on the A1 in advance of our next set of closures, which will allow work to progress on Wentbridge Viaduct and Wentedge Road Bridge.

    During the first six months, our efforts have focussed on Wentbridge Viaduct.

    • We completed the installation of the contraflow and all the work needed to get
      the central reservation surface ready for vehicles.
    • Created a new access route and maintained access for some properties directly
      on the A1.
    • Removed all the southbound bridge surface materials bridge joints and the
      existing waterproofing layer.
    • Started to remove the central reservation platform.
    • Completed the in-depth investigation, inspecting and testing of the deck (bridge
      sections).
    • Drainage investigations across the bridge have taken place.

    Over the last few weeks, our work has concentrated on investigating and testing of the concrete structure. We now have a greater understanding of the scale of work that needs to be done to maintain the lifespan of the bridge, which opened to traffic in 1961, while reducing the need for repairs in the future.

    As a result, we need to revise our original completion estimate for Wentbridge Viaduct from August 2023 to April 2024, in line with the finish date for work on Wentedge Bridge, close by.

    A number of unforeseen issues were uncovered on removal of the road surface and waterproofing layer. These have included a loss of concrete on the concrete deck ends, exposed areas of reinforcement, damage to the maintenance walkway anchor points (under the bridge) and defects to the safety barrier foundations.

    Whilst these issues have not caused a safety risk to the public, we must address them now to ensure they do not worsen and cause future closures for emergency repairs. Unfortunately, the design and approval of these repairs must be completed before the work can be undertaken, which is why you may have noticed periods of inactivity on the bridge itself.

    We can assure you we are working as hard as possible to rectify these issues and have the bridge open to traffic as normal.

    We understand that this revised completion date is disappointing, and that work is causing disruption. This part of the A1 has evolved over many years as opposed to being a purposely built motorway, this means diversion options and alternative routes for drivers are limited.

    We are doing all we can to reduce the impact on drivers and residents. This includes extensive signage from the M25 to Scotch Corner, a considerable number of fixed signs along the A1, B6474, Westfield Lane and village locations including Wentbridge and East Hardwick. We continue to share extensive press, web, and social media updates to ask drivers to use alternative motorway routes.

    We continue to liaise closely with West Yorkshire Police who, when resources allow, are checking traffic on village routes carrying out enforcement on weight restrictions, unsuitable routes for HGVs and speed limits.

    What happens next

    We are now replacing the bridge joints across the viaduct structure and this work started week beginning 24 July under existing traffic management. We will also need three northbound overnight closures so we can carry out some of this work safely on:

    • Monday, Tuesday, and Wednesday, 14, 15 & 16 August 8pm – 6am.

    Existing escort arrangements for residents and diversion routes for vehicles will be in place; we encourage drivers to use the M18 and M62 wherever possible. Vehicles north of Wadworth/Doncaster will use the A628 or A639 – please refer to previous updates on this page for more information on why these routes are in use.

    For a larger version of this map click here

    We apologise for any inconvenience this essential maintenance causes and appreciate your continued patience while we progress the work.

    If you would like to discuss this scheme, or need further information, please contact National Highways on 0300 123 5000 or email ODYNECustomerSupport@nationalhighways.co.uk

     

  • 20 June 2023

    A1 Wentbridge Viaduct and Wentedge Road Bridge June update

    Work to inspect and refurbish Wentbridge Viaduct and Wentedge Road Bridge continues.

    Since work began, we have completed: -

    • Wentbridge Viaduct: accommodation work (creating resident vehicle access) for some of the customers living directly off the A1.
    • Installation of the contraflow and all the enabling work associated with getting the central reserve surface ready for vehicles 
    • All the southbound deck surface materials and the existing waterproofing layer has been removed.
    • The existing bridge joints have been removed.
    • The central reservation platform removal has commenced.
    • In depth investigation, inspecting and testing of the deck is on-going.
    • Drainage investigations across the bridge have taken place.
    • Wentedge Road Bridge enabling work has started.
    • Design work is continuing together with a Temporary Works Design for the propping of the existing bridge deck (for when we remove the central pier).

    What happens now?

    We’ll be carrying out work on the central reservation barrier overnight for three nights on the southbound carriageway. The A1 southbound will be closed between 8pm and 6am on the following dates: -

    • 12, 13 and 14 July 2023

    Residents living directly on the southbound carriageway are being informed by post; the existing access arrangements will be in place.  

    Wentbridge Viaduct: - A small team have been working on and around the bridge to complete inspections and testing of the bridge deck. This work doesn’t involve large plant or machinery and so at times it may look as though no activity is taking place on the bridge.

    There is a great deal of work going on in the background to plan the next phase informed by the results of the inspection and testing.  Once that programme is confirmed, we will share more details with customers and residents.

    Wentedge Road Bridge: - design engineers are working off site to plan the work and some enabling work is underway to prepare the site. The A1 (under the bridge) and Wentedge Road remain open currently.

    Thank you again to residents, businesses, and road users for your patience while we progress this major bridge refurbishment programme.

  • 23 May 2023

    A1 Northbound overnight closure for emergency repair Wednesday 24 May

    We apologise for this late notice - we need to add an additional northbound closure of the A1 between Barnsdale Bar and Ferrybridge Interchange this Wednesday, 24 May, due to a large pothole on the road surface.

    The southbound contraflow is not affected. 

    Traffic will use the diversion routes already in place for closures in this area 8 pm until 6 am. If we complete before that time, the road will open sooner.

    • Northbound high-sided vehicles, traffic north of Wadworth (junction 35) - leave A1 at Barnsdale Bar onto A6201 and onto A628 re-joining A1 from the A645 via Ferrybridge Interchange. The Environmental Weight Restriction for HGVs on A628 Ackworth has been revoked during overnight closures of the A1. This is due to height restrictions on alternate route. 
    • Northbound diversion, traffic north of Wadworth (junction 35) - leave A1 at Barnsdale Bar onto A639, re-joining A1 from the A645 via Ferrybridge Interchange. There are height restrictions on this route. 
    • Northbound diversion - traffic on A1 up to Wadworth (junction 35) - leave junction 35 onto M18 and M62 to Ferrybridge Interchange.

    Thank you for your patience while we complete these emergency repairs. We apologise to residents on the diversion route who may experience increased traffic noise overnight.

  • 15 May 2023

    A1 Southbound overnight closures to work on central barrier - June 2023

    Our next phase of work requires us to ‘cap’ the ends of the central barrier after it was cut to remove a section to accommodate the contraflow, where it crosses over to the other carriageway.

    We will close the southbound carriageway for five nights, Monday to Friday from Monday 5 June to Friday 9 June inclusive from 8pm until 6am each night. If we finish earlier in the week, we will be able to lift the southbound closure to re-open the road.

    For southbound residents at West Park Drive and Grove Hall Lane, existing escorting arrangements, in place to enable access to and from your properties overnight, will be extended to cover these shifts between 8pm and 6am. Please use your existing passes. 

    A fully signed diversion will be in place for all other southbound traffic via the M62 and M18. 

    We apologise for any inconvenience this essential maintenance causes and appreciate your continued patience while we progress the work.  

  • 17 April 2023

    Emergency repair - A1 Wentbridge Viaduct pothole repair

    We apologise for this late notice - we need to add an additional northbound closure of the A1 between Barnsdale Bar and Ferrybridge Interchange this Thursday, 20 April, due to a large pothole on the road surface. This was reported over the weekend and followed up with a temporary repair.

    The southbound contraflow is not affected. 

    Traffic will use the diversion routes already in place for closures in this area 8 pm until 6 am. If we complete before that time, the road will open sooner.

    • Northbound high-sided vehicles, traffic north of Wadworth (junction 35) - leave A1 at Barnsdale Bar onto A6201 and onto A628 re-joining A1 from the A645 via Ferrybridge Interchange. The Environmental Weight Restriction for HGVs on A628 Ackworth has been revoked during overnight closures of the A1. This is due to height restrictions on alternate route. 
    • Northbound diversion, traffic north of Wadworth (junction 35) - leave A1 at Barnsdale Bar onto A639, re-joining A1 from the A645 via Ferrybridge Interchange. There are height restrictions on this route. 
    • Northbound diversion - traffic on A1 up to Wadworth (junction 35) - leave junction 35 onto M18 and M62 to Ferrybridge Interchange.

    Thank you for your patience while we complete these emergency repairs. We apologise to residents on the diversion route who may experience increased traffic noise overnight.

  • 28 March 2023

    Main work starts on Wentbridge Viaduct - April

    Following enabling work during February and March, our major programme of work on Wentbridge Viaduct and Wentedge Bridge will begin after the Easter Bank Holiday. 

    The Wentbridge viaduct work is expected to complete in Autumn 2023, with the Wentedge Road Bridge scheme expected to finish in early 2024.  

    Preparations for the improvements began in early February; we have installed narrow lanes and upgraded the crossover points on the A1 between Barnsdale Bar and Ferrybridge. This is to prepare for the contraflow which will be in place during the main works and enable the work to be carried out as safely as possible. 

    From Tuesday 11 April, there will be a series of overnight full and lane closures (day and night) in place to set up the traffic management for the contraflow: 

    • 11-14 April: The A1 northbound will be closed each night between Barnsdale Bar and Ferrybridge. A fully signed diversion will be in place.
    • 11-14 April: A1 southbound Lane 2 overnight closure between Ferrybridge and Barnsdale Bar.
    • 12-16 April: Lane 2 northbound daytime closure
    • 15-16 April: A1 southbound will be closed between Ferrybridge and Barnsdale Bar on both nights.   
    • 16 April: Lane: 2 southbound daytime closure

    All overnight closures will run between 8pm and 6am the following morning. 

    Northbound & southbound diversion during closures

    • Northbound high sided vehicles, traffic north of Wadworth (junction 35) - leave A1 at Barnsdale Bar onto A6201 and onto A628 re-joining A1 from the A645 via Ferrybridge Interchange. The Environmental Weight Restriction for HGVs on A628 Ackworth, has been revoked during overnight closures of the A1. This is due to height restrictions on alternate route. 
    • Northbound diversion, traffic north of Wadworth (junction 35) - leave A1 at Barnsdale Bar onto A639 re-joining A1 from the A645 via Ferrybridge Interchange. There are height restrictions on this route.
    • Northbound diversion - traffic on A1 up to Wadworth (junction 35) - leave junction 35 onto M18 and M62 to Ferrybridge Interchange. 
    • Southbound diversion traveling beyond Doncaster, M62 and M18 and back onto the A1 at Wadworth.

    From Monday 17 April, the southbound carriageway will be fully closed as the first phase of the works begins.  Traffic travelling in both directions will be in contraflow on the northbound carriageway.  

    Future phases will require traffic to run on the southbound carriageway, and then finally in single lanes in both directions. Details of these phases will be communicated as the scheme progresses. 

    To keep any disruption to a minimum, both structures are being improved using the same traffic management layout, which will include the installation of a contraflow, narrow lanes, and a temporary barrier to keep the workforce safe. Switches between the phases will require a number of overnight full closures to alter the traffic management. A fully signed diversion will be in place. 

    These are essential works which will improve journeys on this important route and minimise disruption by reducing the number of works on this section of the A1 in the future. 

    We do unfortunately expect some disruption while this is carried out. We apologise in advance to drivers and residents close to the work for disruption, and we thank them in advance for their patience. 

    We strongly advise people planning to travel in this area to plan their journeys in advance and allow more time to reach their destination. 

    We are working hard to keep traffic on our motorway network as much as possible; however, in instances when traffic needs to be diverted on to local roads, we are asking drivers to follow the fully signposted diversions. 

  • 17 March 2023

    Enabling works - update on overnight closures

    Enabling work to establish a contraflow on the A1 between Barnsdale Bar and Ferrybridge Interchange is progressing well although we have experienced some delays due to recent bad weather. 

    Due to heavy snow, a number of overnight shifts had to be cancelled on the southbound carriageway; these have now been rescheduled for the following dates:- 

    • Thursday 30 March
    • Friday 31 March 
    • Monday 3 April 

    We will be contacting customers who live directly on the A1 southbound to update you about our plans. Existing escorting arrangements in place to enable access to and from your properties overnight will be extended to cover the extra shifts, between 8pm and 6am.  

    Northbound closures are not affected and will continue as planned on the following dates:-

    • Monday 20 March 
    • Tuesday 21 March 
    • Wednesday 22 March  

    We apologise for any inconvenience these additional dates may cause and appreciate your patience while we prepare the carriageway for the contraflow.  

  • 14 February 2023

    Public information event - your feedback

    On Saturday 11 February we held a public information event at Darrington Golf Club for local residents and road users with questions about our work at Wentbridge and Wentedge, on the A1. 

    We would like to say thank you to everyone who attended; your questions and feedback will help us to continually review the impact of the work and inform concise methods of communication. 

    We were also pleased to meet a resident who worked on Wentbridge Viaduct following it's opening in 1961, as an employee of the former West Riding County Council. 

    Meeting room and presentation, Wentbridge.

    Here is a summary of some of the key questions raised, and our answers.

    Why are HGVs being diverted through Ackworth when there is a weight restriction?

    We are signing high sided vehicles (not all HGVs) through Ackworth on the A628 during our eight northbound overnight closures as this is the only route available due to height restrictions on the A639 (a low bridge).  

    When choosing a diversion route, there are many factors to be considered such as height and weight restrictions, access to properties, impact on communities and the road alignment. When we have to divert onto local roads, we are led by the local authority who advise us of options and approve the final route. 

    Wakefield Council enforce the environmental weight restriction which is in place on a section of the A628 in High Ackworth. This is not a structural weight limit, but one in place to reduce HGV movements through the village. As there are no other options for high sided vehicles, this restriction has been revoked while the overnight closures are in place. 

    As soon as our eight overnight closures are completed, the restriction will be put back in place and this will continue to be enforced by Wakefield Council and West Yorkshire Police. 

    We will continue to signpost all other northbound traffic to use the M18 and M62, south of junction 35 and for traffic north of Doncaster, we are signposting to a diversion on the A639 with the exception of high sided vehicles. 

    Why can't traffic be diverted onto Went Lane and Ackworth Road Featherstone?

    Whilst we accept the A628 is not an ideal diversion route for all vehicles (given the narrow sections of road and proximity to properties), the alternative route suggested by some residents of using Went Lane and Ackworth Road Featherstone for example is equally if not more, unsuitable.

    The proposed route is an A road whereby the alternative is a B road; Went Lane also has narrow sections along its length including a ‘shuttle working’ traffic signal arrangement to control traffic flow over the River Went. Furthermore, the junction of Ackworth Road and Pontefract Road would struggle to physically accommodate large vehicles when stopped (or queued) at the traffic signals, potentially gridlocking the east and west bound directions along the A645 due to the one-way traffic flow arrangement at the junction.

    HGV traffic that is low enough to clear the low bridge at Hardwick Road Pontefract will be encouraged to use the A639 and only those over height HGVs will take the more circuitous route along the A628. This should mean only a small number of HGVs will be required to use the A628, although it is recognised that the desire would be to have none of these vehicles along this route.

    As a result, on this occasion, we must send high sided vehicles along the A628.

    How will you deter traffic from using the A1 during the main work?

    • We are signing the roadworks from the M25, Peterborough and Scotch Corner to advise customers of likely delays and are asking them to consider using the M18, M62 or M1 where possible, before they join queuing traffic. 
    • We are using our channels to ask haulage companies to plan ahead, use alternative routes and not to follow sat navs onto unsuitable roads in Wentbridge, East Hardwick and the surrounding villages.  
    • We will have mobile electronic signage on the approach to the closure to advise customer of real time queuing information during peak times.  
    • We have placed extensive static signage in the local area to advise drivers of unsuitable roads and no through roads. Following this meeting, we will add others to areas which were highlighted by local residents, after consultation with Wakefield Council. 
    • We are asking people to avoid using their satnavs. Our variable messaging signs will instruct drivers of the most suitable route to take. Drivers can also keep up to date with our real time updates on Twitter - @HighwaysYORKS or www.trafficengland.co.uk

    Will the southbound petrol station and services be open? 

    Yes, when the main work starts and the A1 between Barnsdale Bar and Ferrybridge is under contraflow, the BP garage will be open as it sits outside the crossover points and contraflow. 

    What’s the plan for the new A1 Doncaster to Darrington road scheme?

    A1 Doncaster to Darrington is a Roads Investment Strategy (RIS3) Pipeline scheme. The RIS3 Pipeline is made up of 32 potential future schemes and all schemes are being assessed against a broad range of criteria including value for money, affordability, the environment and deliverability.

    We’re working on providing as much information to the Department for Transport who will consider the next steps as a portfolio of schemes. The pipeline schemes remain uncommitted until the government publishes the Roads Investment Strategy 3 (RIS3): 2025-2030. Only then will we know which schemes will be taken further. The final decision will rest with the government. 

    Other comments 

    • Resident comments on a water run off issue near Wentbridge Viaduct.
    • Length of notice for residents living in Ackworth re customer letters.
    • Individual comments and queries from those residents living directly on the A1.
    • Queries around litter and welfare facilities for the workforce.
    • Potential of congestion in Pontefract town centre at Town End.
    • Questions about through traffic in Wentbridge, East Hardwick and Westfield Lane. 

    Thank you to everyone for your attendance at this event; we are looking at all the feedback and comments to help inform our plans and how we monitor the impact on residents and drivers as the work gets underway. 

  • 06 February 2023

    Diversions - A1 Wentbridge Viaduct and Wentedge bridge - enabling work February and March

    The following diversions are in place for overnight closures on the A1 between Barnsdale Bar and Ferrybridge Interchange. 8pm while 6am. You can download a copy of this map at the end of this page. 

    Diversion (closures in both directions, but not at the same time/dates - for dates please see below). 

    • Northbound high sided vehicles, traffic north of Wadworth (junction 35) - leave A1 at Barnsdale Bar onto A6201 and onto A628 re-joining A1 from the A645 via Ferrybridge Interchange. The Environmental Weight Restriction for HGVs on A628 Ackworth, has been revoked during overnight closures of the A1. This is due to height restrictions on alternate route. 
    • Northbound diversion, traffic north of Wadworth (junction 35) - leave A1 at Barnsdale Bar onto A639 re-joining A1 from the A645 via Ferrybridge Interchange. There are height restrictions on this route.
    • Northbound diversion - traffic on A1 up to Wadworth (junction 35) - leave junction 35 onto M18 and M62 to Ferrybridge Interchange. 
    • Southbound diversion - traveling beyond Doncaster, M62 and M18 and back onto the A1 at Wadworth.

     Diversion map for A1

     

  • 03 February 2023

    Closures during enabling works

    Enabling works and closures 

    Ahead of the main programme, enabling work will take place to allow National Highways to install the contraflow. Engineers will upgrade contraflow crossover points, strengthen drainage covers and other survey work. The enabling work will start on Monday (6 February) and is due to complete in March.  

    This will mean the closure of the northbound carriageway from Barnsdale Bar to Ferrybridge Interchange overnight, between 8pm-6am, on the following dates:    

    • Monday 6 February 
    • Tuesday 7 February 
    • Friday 10 February 
    • Monday 13 February 
    • Tuesday 14 February  
    • Monday 20 March 
    • Tuesday 21 March 
    • Wednesday 22 March  

    In addition, the southbound carriageway from Ferrybridge Interchange to Barnsdale Bar will be closed overnight between 8pm-6am, on the following dates:  

    • Wednesday 8 February – Thursday 9 February 
    • Wednesday 15 February – Friday 17 February 
    • Monday 20 February – Friday 24 February 
    • Monday 27 February – Friday 3 March 
    • Monday 6 March – Friday 10 March 
    • Monday 13 March – Friday 17 March  

    These closures will allow the installation of narrow lanes on the carriageway to keep traffic flowing on this route. A temporary safety barrier will also be installed to keep the workforce safe throughout the work and separate opposite flowing traffic. 

    A fully signed diversion route will be in place.    

    Information event at Darrington Golf Club 

    To help nearby residents get more information about this work, National Highways is holding a drop-in information day at Darrington Golf Club on Saturday 11 February  10am – 1pm. This is an opportunity for people to meet the team behind the programme and express any concerns they have about the work, or to find out more about what is taking place.    

  • 16 January 2023

    A1 Wentbridge Viaduct and Wentedge Road Bridge - enabling work to start 6 February

    Following several reactive repairs, we need to carry out a structural inspection and renew the waterproofing layer on the viaduct at Wentbridge. We also aim to complete major repairs to Wentedge Road Bridge at the same time.

    We plan to start this work in April 2023 and aim to finish winter 2023.  This work is substantial and is likely to cause disruption to customers travelling on the A1. 

    Before we start in April, we need to complete some enabling work as we plan to install a contraflow on the A1. The enabling work includes upgrading contraflow crossover points, strengthening drainage covers and other survey work. We aim to start the enabling work on 6 February and plan to complete in March.

    To complete this safely. we will need a mixture of lane closures and full closures overnight between 8pm-6am, Monday to Friday.

    • Southbound – Full closure
    • Northbound – Full closures and mix of lane closures

    We have contacted residents living directly off the A1 southbound with an outline of our plans so they can talk to us about maintaining access to their properties.  

    We have liaised with the local council and updated parish and ward Councillors about our intention to carry out this work. 

    When we have confirmed a programme for our work, we will be able to update more customers with further details, includes information about closures and diversions. 

    For detailed background information about this work, please see our previous updates.  

  • 13 January 2023

    Essential maintenance planned for 2023

    We’ll soon be carrying out substantial maintenance work on the Grade ll listed A1 Wentbridge Viaduct and on nearby Wentedge Road Bridge located near Wentbridge village, West Yorkshire.

    Wentbridge Viaduct from below

    Following a regular inspection and reactive repairs, we need to carry out a detailed structural inspection of the viaduct at Wentbridge. At the same time, we plan to replace the waterproofing layer, road surface, road markings and studs on the carriageway in both directions.

    We also aim to complete major repairs to Wentedge Road Bridge which include replacing the central pier, waterproofing, surfacing and parapet replacement, utilising the same road closure.

    We need to do this work now to prevent further maintenance issues with the structures, reducing the need for reactive repairs in the future. Carrying out this work at the same time also means less disruption for customers in the longer term.

    We plan to start the main work in April and aim to finish in around six months.

    Our design team and engineers have spent some time looking at how this work can be carried out with the least disruption to customers and residents. This is a real challenge due to the importance of this route and the impact of diversions, especially on local people and hauliers moving goods around the country.

    We’ll be getting in touch with local communities when we have finalised these plans.

    In the meantime, keep in touch as we update this page by signing up for A1 email updates using the Sign Up for Updates link on the right.

    (Photo - Alan Murray Rust via Creative Commons) 

Project information

Overview

Wentbridge viaduct bridge, which opened to traffic in 1961, is a concrete motorway bridge carrying the A1 over the River Went. Wentbridge village sits immediately west of the bridge with Brockerdale Nature Reserve to the east.

Wentbridge viaduct is an internationally renowned structure; it was chosen to feature in the Twentieth Century Engineering Exhibition at New York's Museum of Modern Art and is a heritage listed building.

Archive image - Wentbridge Viaduct construction and scaffold

“The deck is of post-tensioned concrete, with six box cells, and sits on inclined cellular reinforced concrete legs which are pinned at top and bottom, with precast concrete hinges. The prestressing cables are external to the box webs and are continuous over the full 143m length of the deck. This was the first use of external prestressing in the UK. Additional internal cables are provided in the top slab over the piers, and vertical prestressing is used to counteract shear in the side spans”  (Credit - http://happypontist.blogspot.com/)

The bridge needs several essential repairs in addition to our regular maintenance, these repairs were identified during recent inspections of the structure.

While the road is closed, we’ll also use the time to make more detailed inspections of the bridge and complete other repairs nearby at Wentedge Road Bridge.

We are replacing the central pier at Wentedge Rd Bridge plus associated works on the top of the structure including replacement of the parapets, joints, and surfacing.

These are substantial repairs; we may need to revise timescales once the extent of the repairs are uncovered. 

We’re making several essential repairs and improvements for safer and smoother journeys for customers; this work will extend the life of each bridge and reduce the number of reactive repairs and unplanned road closures on this route. 

Why has the completion date changed to Summer 2024?

We started enabling work in April of 2023 by installing a contraflow on the viaduct. This allowed us to remove road surface layers to conduct in depth inspections and investigations. Since removing the road surface, several issues were uncovered, and those issues meant we have had to revise our programme of work. Once we were aware of the extent of the repairs and had solutions to address them, we adjusted our completion date to April 2024. We have taken the decision to revise this date again to the summer 2024, considering remedial work required on Wentedge Bridge, so we can stand down this part of the project.

We are deferring the work on Wentedge Bridge while we work behind the scenes on a new design for the central pier and the engineering solutions required to prop the structure. This means once northbound work on Wentbridge Viaduct is complete, we can re-open this part of the A1. We aim to return during 2026 to complete Wentedge Bridge. As this is a busy part of the A1, we may need to return before then to carry out other routine repair work as part of our day-to-day management of the network.

Why has there been little or no activity on the viaduct?
Once the repairs were identified it took some time to design, check and approve the engineering solutions. When those repairs got underway, they required up close and invasive working methods, often with hand tools. This is because we need to protect the post-tensioned cables within the bridge from any damage. We did not need large plant machinery for this phase, so at times it can appear less busy. We also had
several repairs which were accessed from underneath the structure.

Why are your workers in vehicles, shouldn’t they be fixing the bridges?
For safety and security reasons, our traffic management (the contraflow and access onto the work area) is staffed 24/7. It is the role of our traffic management contractor to monitor access into the work area, adjacent compound, and site office. Traffic management contractors do not carry out work on the roads, they are there to support safe working and ensure no unauthorised vehicles enter the work area.

Can you work 24/7 to complete the maintenance sooner?
We continue to work on site using a mix of daytime and evening shifts and where resources are available, at the weekends. There may be times when there is less activity on the bridge as concrete is curing and we carry out work behind the scenes and underneath, below the deck. No activity does not mean we are not working on this project – at any one time we have a large team of engineers and contractors working to refurbish the bridge and progress the project.

Are both the viaduct and bridge safe? Would it be quicker to build a new one?
Yes, they are safe and there is plenty of life left the viaduct. Building a new viaduct is not necessary, this would be more disruptive and would not represent value for money at this time as our extensive testing shows the integrity of the viaduct is overall, in good condition. Wentedge Bridge is safe to use, and recent inspections will help inform work in the future.

Why is so much traffic diverted through local villages? What can you do to stop this?
We are not diverting or signposting any traffic through local roads while the A1(M) is open, under contraflow. Drivers are making these decisions independently or are choosing to follow their Satnavs. Unless there is a restriction in place, it is perfectly legal for drivers to make those choices although we understand that this impacts on local residents. We have placed extensive signage across all local villages, including ‘no access for HGV (Heavy Goods Vehicle)’ and ‘local access only’ signage on unsuitable roads,
balancing this with signage requests from local businesses, who are still open and trading.

We are doing all we can to keep drivers updated about any delays and are advising road users to expect some delays on the A1(M) or are signposting to the M18 and M62, using signage from Scotch Corner to the M25.

Drivers are speeding through villages – what can you do to stop this?
We have met with residents including parish councils to see how we can support safe driving behaviour. As a result, we have safety camera vehicles operating in the area and the Police are actively enforcing speed limits, weight, and height restrictions on local routes.

How do I report maintenance issues on the local roads?
The local road network is under the management of Wakefield Council or North Yorkshire Council. We continue to meet and liaise with the local authorities on a regular basis; they are fully aware of our work and the challenges for drivers and residents. We are not diverting traffic onto these local routes, except during full overnight closures and these have been minimal. If you spot any emergency repair issues, these should be reported to the council on their website or 24/7 customer service phone number.

What are the queuing times like on the A1(M)? How long will I be delayed?
Our electronic monitoring shows that on average, queuing times are around 30 minutes at peak times before getting through the contraflow – staying on the A1(M) or using the M18/M62 as an alternative, are the best routes to follow for all traffic.

Some drivers are using Darrington Lane to come off the A1 and then re-join, to try and get ahead of queuing traffic. This is causing congestion in Darrington. There is as a lot of unnecessary traffic going around the roundabout. Could traffic lights be fitted on the southbound slip road as a deterrent? On the A1, drivers are also using the ‘hard shoulder’ area to get around vehicles. Can you barrier the verge to stop those using it illegally?
We are aware of these issues and have looked at several options. Trying to re-join the A1 using the roundabout off Darrington Lane has no positive outcome – no time is saved by taking this route during peak times. While this behaviour may add to the congestion, choosing to take this route is perfectly legal and there are no powers to enforce any restrictions.

We will continue to sign the correct route through the contraflow and share information with drivers to help plan journeys. There is no hard shoulder in this area as there is not enough room, instead the road surface has a restricted area as shown by the raised white lining near the verge. Using this area to jump traffic is an offence – we cannot barrier or cone this area as emergency vehicles still need access, as they would a hard shoulder. However, as a result of driver behaviour, we have installed a safety camera in this location. The Police are aware of the issue and are enforcing the restriction.

Where are you diverting traffic when the A1 is closed?
Drivers are advised to stay on the motorway network where possible using the M62 and M18 for both northbound and southbound journeys.

 Northbound diversion - traffic on A1 up to Wadworth (junction 35) - leave junction 35 onto M18 and M62 to Ferrybridge Interchange.

 Northbound high-sided vehicles, north of Wadworth (junction 35) - leave A1 at Barnsdale Bar onto A6201 and onto A628 re-joining A1 from the A645 via Ferrybridge Interchange. The Environmental Weight Restriction for HGVs on A628 Ackworth has been revoked during overnight closures of the A1. This is due to height restrictions on alternate route.

 Northbound diversion, traffic north of Wadworth (junction 35) - leave A1 at Barnsdale Bar onto A639, re-joining A1 from the A645 via Ferrybridge Interchange. There are height restrictions on this route.

 Southbound traffic use the M62 and M18


What have you done to keep people informed about this work?
We began advance communications in January 2023 through the local media, councillors, and parish councils, four months ahead of our start date. We also sent updates to local MPs (Member of Parliament) and continue to do so.

We held a public information event in February in Darrington and are looking to repeat this on Saturday 10 February 2024.

We have sent written updates to over 2000 residents, at several stages of the project and communicate with distribution and logistics companies by email or newsletters, so they can plan.

The project team also continue to respond to residents' questions on an individual basis in person, by email and over the phone.

We are sharing regular updates in the press, on our website and social media channels to keep drivers, businesses and residents informed.

Where can I find real time updates about any delays and closures?
Real time information about closures is available from National Highways by visiting www.trafficengland.com and the X (formally Twitter) account @HighwaysYorks.

We’ll also be updating our Facebook page, National Highways Yorkshire - although this is not managed 24/7.

For urgent real-time assistance, our 24/7 contact centre team can also provide up-to the minute information on 0300 123 5000.

Other enquires can be sent to our regional customer service team by email at info@nationalhighways.co.uk

We are hosting a second public information event, before the contraflow switch takes place, at Darrington Golf Club. You are welcome to attend to ask questions or speak with the Project Team directly.

Place: Darrington Golf Club, Havercroft Lane, Darrington, Pontefract WF8 3BP
Time: 10am.
Date: Saturday 10 February 2024

The session is expected to last around two hours, please arrive for 9.45. The venue is fully accessible and free parking is available.

If you are unable to attend, we have an updated ‘frequently asked questions’ update for your information. These are questions put to us recently by residents and drivers, online and in person.

Alongside our Yorkshire supply chain, contractors and suppliers, we are supporting good causes in the community while we complete our work on the A1. 

You can read more about the projects and places we are helping here

Public information event - your feedback

On Saturday 11 February we held a public information event at Darrington Golf Club for local residents and road users with questions about our work at Wentbridge and Wentedge, on the A1. 

We would like to say thank you to everyone who attended; your questions and feedback will help us to continually review the impact of the work and inform concise methods of communication. 

We were also pleased to meet a resident who worked on Wentbridge Viaduct following it's opening in 1961, as an employee of the former West Riding County Council. 

Meeting room. public seating, speaker at the front.

Here is a summary of some of the key questions raised, and our answers.

Why are HGVs being diverted through Ackworth when there is a weight restriction?

We are signing high sided vehicles (not all HGVs) through Ackworth on the A628 during our eight northbound overnight closures as this is the only route available due to height restrictions on the A639 (a low bridge).  

When choosing a diversion route, there are many factors to be considered such as height and weight restrictions, access to properties, impact on communities and the road alignment. When we have to divert onto local roads, we are led by the local authority who advise us of options and approve the final route. 

Wakefield Council enforce the environmental weight restriction which is in place on a section of the A628 in High Ackworth. This is not a structural weight limit, but one in place to reduce HGV movements through the village. As there are no other options for high sided vehicles, this restriction has been revoked while the overnight closures are in place. 

As soon as our eight overnight closures are completed, the restriction will be put back in place and this will continue to be enforced by Wakefield Council and West Yorkshire Police. 

We will continue to signpost all other northbound traffic to use the M18 and M62, south of junction 35 and for traffic north of Doncaster, we are signposting to a diversion on the A639 with the exception of high sided vehicles. 

Why can't traffic be diverted onto Went Lane and Ackworth Road Featherstone?

Whilst we accept the A628 is not an ideal diversion route for all vehicles (given the narrow sections of road and proximity to properties), the alternative route suggested by some residents of using Went Lane and Ackworth Road Featherstone for example is equally if not more, unsuitable.

The proposed route is an A road whereby the alternative is a B road; Went Lane also has narrow sections along its length including a ‘shuttle working’ traffic signal arrangement to control traffic flow over the River Went. Furthermore, the junction of Ackworth Road and Pontefract Road would struggle to physically accommodate large vehicles when stopped (or queued) at the traffic signals, potentially gridlocking the east and west bound directions along the A645 due to the one-way traffic flow arrangement at the junction.

HGV traffic that is low enough to clear the low bridge at Hardwick Road Pontefract will be encouraged to use the A639 and only those over height HGVs will take the more circuitous route along the A628. This should mean only a small number of HGVs will be required to use the A628, although it is recognised that the desire would be to have none of these vehicles along this route.

As a result, on this occasion, we must send high sided vehicles along the A628.

How will you deter traffic from using the A1 during the main work?

  • We are signing the roadworks from the M25, Peterborough and Scotch Corner to advise customers of likely delays and are asking them to consider using the M18, M62 or M1 where possible, before they join queuing traffic. 
  • We are using our channels to ask haulage companies to plan ahead, use alternative routes and not to follow sat navs onto unsuitable roads in Wentbridge, East Hardwick and the surrounding villages.  
  • We will have mobile electronic signage on the approach to the closure to advise customer of real time queuing information during peak times.  
  • We have placed extensive static signage in the local area to advise drivers of unsuitable roads and no through roads. Following this meeting, we will add others to areas which were highlighted by local residents, after consultation with Wakefield Council. 
  • We are asking people to avoid using their satnavs. Our variable messaging signs will instruct drivers of the most suitable route to take. Drivers can also keep up to date with our real time updates on Twitter - @HighwaysYORKS or www.trafficengland.co.uk

Will the southbound petrol station and services be open? 

Yes, when the main work starts and the A1 between Barnsdale Bar and Ferrybridge is under contraflow, the BP garage will be open as it sits outside the crossover points and contraflow. 

What’s the plan for the new A1 Doncaster to Darrington road scheme?

A1 Doncaster to Darrington is a Roads Investment Strategy (RIS3) Pipeline scheme. The RIS3 Pipeline is made up of 32 potential future schemes and all schemes are being assessed against a broad range of criteria including value for money, affordability, the environment and deliverability.

We’re working on providing as much information to the Department for Transport who will consider the next steps as a portfolio of schemes. The pipeline schemes remain uncommitted until the government publishes the Roads Investment Strategy 3 (RIS3): 2025-2030. Only then will we know which schemes will be taken further. The final decision will rest with the government. 

Other comments 

  • Resident comments on a water run off issue near Wentbridge Viaduct.
  • Length of notice for residents living in Ackworth re customer letters.
  • Individual comments and queries from those residents living directly on the A1.
  • Queries around litter and welfare facilities for the workforce.
  • Potential of congestion in Pontefract town centre at Town End.
  • Questions about through traffic in Wentbridge, East Hardwick and Westfield Lane. 

Thank you to everyone for your attendance at this event; we are looking at all the feedback and comments to help inform our plans and how we monitor the impact on residents and drivers as the work gets underway. 

Documents

Traffic information

Information about scheduled roadworks and events on our motorways and major roads.

Sign up for updates!

Keep up to date with what's happening on this scheme by signing up to our updates.

Feedback