M25 junction 10 project profile

The three-year project, due for completion in summer 2025, will reduce congestion, create a smoother flow of traffic and provide safer journeys for thousands every day.

M25 junction 10 project profile

Location: A few miles north of Guildford in Surrey

Project managed by: National Highways

Status: Work in progress

Progress in autumn 2024

Through autumn, we've achieved some significant project milestones.

Jet lanes

Over two weekends in October, we built the 'jet lanes' that will carry traffic swiftly through the new junction.

Due to good progress over those weekends, we didn't need a further closure in November. This paved the way for us to install Clearmount Bridge. 

Clearmount Bridge

Clearmont Bridge is a bridleway for pedestrians, cyclists and horse-riders crossing over the motorway.

We built the 450-tonne bridge off-site over summer. Once we finished building new supports on either side of the motorway, we installed the bridge over 2 and 3 November.

We used heavyweight transporters to move the bridge 300 metres along the M25 and jack it into place. With the new bridge safely installed, we managed to reopen the road to traffic more than two hours ahead of schedule.

This is the first time we've used this this method on the M25. It meant we could avoid closing the M25 for a full weekend. We'll open the bridge at a later date. 

Wisley Lane Bridge

We've finished work on Wisley Lane Bridge which we'll open to traffic on Monday 11 November. The new bridge provides access to Wisley Lane and the RHS Garden Wisley.

At the same time, we'll permanently close the existing access to and from the A3 at the old Wisley Lane.

What else have we achieved in 2024?

Demolishing the old Clearmount Bridge

The project reached a key landmark in March with the demolition of Clearmount Bridge, the first of several demolitions scheduled to take place during 2024.

It involved a full weekend closure of the junction, and produced 3,000 tonnes of material, which took 80 trucks more than 24 hours to clear away.

We also installed a huge gantry that spans the width of the M25. At 58 metres long and weighing nearly 130 tonnes, we needed a 70-tonne crane to lift it.

Largely thanks to many drivers avoiding the area and making other travel plans during the closure, the operation was a great success and we were able to re-open the junction ahead of schedule.

Our gallery shows the main stages of the bridge demolition and the superspan gantry installation, which took place over the weekend 15 to 17 March.

Installing news east and west bridges

A second weekend closure took place in May. It allowed for the installation of a new east bridge consisting of 68 beams, each weighing 16 tonnes, and another four beams weighing 40 tonnes.

The closure was in place from 9pm on Friday 10 May. Due to good progress being made throughout the weekend by the project team, we were able to reopen the road on Sunday evening, seven hours ahead of schedule.

Our third and final full weekend closure of 2024 mirrored our May bridge installation on the opposite side of the junction.

From Friday 12 July to Sunday 14 July, we installed the west bridge, together with a signal gantry spanning the full width of the carriageway. Once again, we were able to re-open the road ahead of schedule around 11pm on Sunday night.

What happens next?

We'll be:

  • making more changes to the gyratory
  • installing more bridges, including the green bridge at Cockcrow
  • restoring heathland and planting new trees as part of our pledge to make environmental improvements

We'll need two more M25 full weekend closures in 2025, which we'll announce on our  M25 junction 10 project page.

You'll also find the latest information about forthcoming closures and diversion routes on this page

The following graphic shows the bridges to be constructed and demolished as part of the project. Blue bridges are to be constructed; red bridges are to be demolished.

Graphic showing M25 junction 10 bridges

1 Wisley Lane footbridge

2 Wisley Lane / NMU bridge

3 Cockcrow bridleway bridge

4 Cockcrow green bridge 

5 Redhill Road bridleway bridge

6 Clearmount bridleway bridge

7 Clearmount bridleway bridge

8 Northern gyratory bridge

9 Northern gyratory bridge

10 Southern gyratory bridge

11 Southern gyratory bridge

12 Sandpit Hill NMU bridge

About the junction

The M25 junction 10 and A3 Wisley interchange is the busiest section of the M25, with over 300,000 vehicles travelling through it every day. Journeys that include commuters, businesses, those visiting local attractions and holiday makers.

This sheer volume of traffic means vehicles often start queuing northbound between Ockham Park roundabout and the M25 junction 10, on the junction 10 roundabout, and on the approach to the Painshill roundabout.

The junction is located among some rare and beautiful habitats including the heathland at Wisley and Ockham commons.

What is the project?

The three-year project, due for completion in summer 2025, will reduce congestion, create a smoother flow of traffic and provide safer journeys for thousands every day.

We’ll also deliver environmental improvements, including the restoration of heathland around junction 10, and the planting of new trees and woodland in other areas.

The A3 will be surfaced with a low-noise material and environmental barriers along the M25 will be replaced. The effects on air quality will be minimised, and local rivers, lakes and ponds will be better protected from pollution and flooding.

Exploring the area on bicycle, foot or horse will be easier, with new bridges crossing the A3 and M25, connecting the four quadrants surrounding junction 10 for the first time.

Key features of the scheme:

  • An additional lane on the A3 in both directions from Ockham and Painshill junctions towards the M25
  • A larger roundabout with extra lanes to increase capacity
  • Free-flow left turns at all four corners of the junction
  • Improvements to the A245 Seven Hills junction and Painshill roundabout
  • Safer access to Old Lane, Elm Lane, Heyswood campsite and San Domenico
  • Improvements to the local environment and wildlife
  • New and safer routes for cyclists, pedestrians and horse-riders

Artist's impression of the new heathland bridge

The UK’s first heathland green bridge will reconnect the commons either side of the A3, and provide a natural and safe corridor for wildlife.

Feedback