M11 junction 6 to 13 maintenance work
We’re carrying out essential maintenance work on M11. This will ensure the M11 will continue to remain in a safe and serviceable condition.
Latest updates
-
29 October 2024
M11 southbound junction 10-9 surface renewal
We’re going to carry out road surface repairs to the M11 southbound carriageway between junctions 10 and 9. Once complete, drivers will benefit from a safer, smoother road surface.
We plan to complete this work over two nights between Wednesday 6 November and Saturday 9 November. We will work between 9pm to 5am, weather permitting.
Closures and diversions
To carry out the work safely, we will need to close the M11 southbound between junctions 10 and 9.
If you are traveling this route:
- leave the M11 at junction 10 onto the A505
- proceed eastbound until you join the A11
- at the A11 Fourwentways Interchange, head southbound on the A11
- rejoin the M11 at junction 9
-
24 October 2024
M11 junction 7a to 8 resurfacing
Our essential resurfacing work on the M11 between junctions 7a and 8 southbound and northbound is going well. Once complete, drivers will benefit from a safer and smoother road surface.
We plan to complete the next phase over six nights between Monday 11 November and Sunday 17 November 2024. We'll work between 9pm and 5am, weather permitting.
Closures and diversions
To carry out the work safely, we will need to close the M11 one direction at a time, and divert traffic as detailed below:
Monday 11 to Saturday 16 November
M11 northbound junction 7a to 8
- You'll be diverted via the A1025, A414, A10 and A120
- At junction 8 of the M11, continue your journey northbound
Saturday 16 to Sunday 17 November
M11 southbound junction 8 to 7a
- You'll be diverted via the A120, A10, A414 and A1025
- At junction 7a of the M11, continue your journey southbound
M11 junctions 7a to 8 northbound and southbound closure and diversion route
-
21 October 2024
M11 northbound junctions 6 to 7 resurfacing
We’re planning essential resurfacing work on the M11 northbound carriageway between junctions 6 to 7. This will include refreshing the road markings. Once complete, drivers will benefit from a safer and smoother road surface.
We plan to complete this work over three nights between Friday 25 October and Monday 28 October. We will work between 10pm and 5am, weather permitting.
Closures and diversions
To carry out the work safely, we will need to close the M11 northbound carriageway between junctions 6 and 7 and divert traffic.
Drivers travelling this route should:
- exit the M11 at junction 6 and join the M25 westbound
- exit the M25 at junction 25 and join the A10 northwards
- then exit at the Hailey Interchange and continue along the A414
- rejoin the M11 at junction 7
Please remember that closures can change at short notice. You can check the latest information on our daily closures page or find live travel information on our Traffic England website. Our travel alerts give details of live incidents on our network.
-
13 September 2024
LED lighting upgrades at M11 junction 8 and A120 fast link exit slip
We're upgrading the lights at M11 junction 8 and on the A120 exit slip to more energy-efficient LED lights to help reduce carbon emissions.
LEDs are much better for the environment, use less energy, and last longer, which means fewer road closures for repairs and safer roads overall.
The work will take about 11 weeks, starting from Monday 23 September to Friday 6 December 2024. We'll be working overnight from 9pm to 5am, Monday to Friday, depending on the weather.
Closures
- Lane closures on the M11 at junction 8 for the LED lighting upgrades.
- The A120 fast link exit slip will be closed for 7 nights, from Thursday 7 November to Friday 15 November 2024.
Diversions
A120 eastbound traffic will be diverted:
- Exit the M11 onto Birchanger roundabout.
- Continue eastbound on the A120 to Priory Wood Roundabout.
- Continue your journey towards London Stansted Airport/Dunmow.
Please remember that closures can change at short notice. You can check the latest information on our or find live travel information on our Traffic England site. Our travel alerts give details of live incidents on our network.
-
01 July 2024
Final phase of resurfacing to begin
We're about to start the final phase of our resurfacing work on the M11 between junctions 6 and 10. As well as resurfacing, we'll also be be replacing the road studs (cat's eyes).
Work is progressing well, and we plan to complete this final phase over 4 weeks starting on Friday 5 July 2024.
This work will require some road/lane closures. Please remember that closure details can change at short notice. For the most up-to-date information, please visit our daily closures page.
Diversion routes
M11 southbound junctions 8 to 6 diversion
Project information
Overview
Our works on M11 Junction 8 will replace waterproofing material that has reached its end of life, and is no longer protecting the concrete structure of the bridge, these are essential works to ensure the life-span of the bridges at this junction.
We are also carrying out essential resurfacing, road marking and drainage renewal between junction 7 and junction 10. This will keep the road in a safe and serviceable condition.
Essex Highways are carrying out works to increase capacity and help meet future network demand on junction 8 of the M11, by widening the A120 signalised junction. These works are separate to the ones we are carrying out.
You can find more information about these works on the Essex County Council M11 junction 8 improvement scheme webpage. You can also contact Essex County Council via email at m11J8@essexhighways.org.
Benefits
The works will ensure the life-span of the bridges at this junction, and will keep the road in a safe and serviceable condition.
Documents
Traffic information
Information about scheduled roadworks and events on our motorways and major roads.X