M62 Junctions 25 to 30 Dynamic Hard Shoulder enhancements

We are upgrading dynamic hard shoulder motorways – starting with the central reservation barriers

Start date April 2022
End date Autumn 2023
Cost TBC

Latest updates

  • 26 October 2023

    Main work completed - Autumn 2023

    Our main work on the M62 junctions 25 to 30 is complete.

    We were able to remove the traffic management in September, reducing the impact on drivers. 

    We have some outstanding work which includes sign updates and painting. To complete this we will work overnight when the motorway is less busy, using lane closures.

    We would like to thank drivers for their patience while we delivered this programme of essential safety enhancements. 

Project information

Overview

The barrier upgrade has been developed as part of our work to upgrade Dynamic Hard Shoulder motorways to the latest safety standard.

On 15 April 2023 the Government announced that plans for new smart motorways would be cancelled in recognition of the lack of public confidence felt by drivers and cost pressures. This follows an announcement in January 2022 to pause new smart motorways.

Plans to convert these sections of motorway to the latest All Lane Running standard have been cancelled. In the Government's response to the 2021 Transport Select Committee report into smart motorways it committed to consider alternative ways in which to operate dynamic hard shoulder motorways.

The Government and National Highways continue to invest £900 million in further safety improvements on existing smart motorways, and to give motorists clear advice when using existing smart motorways.

We are installing further safety measures for DHS motorways in operation, including upgrading the central reservation barrier.

Work will get underway this month in Yorkshire on a 1.7-mile section of the M62 between junctions 26 at Chain Bar and 28 at Tingley. Construction starts on 19 April and is expected to be complete in the Autumn

Three lanes will remain open to traffic, with lane 4 closed and lane 3 slightly narrowed. There will be a reduced 50mph speed limit while work is being carried out. Occasional overnight closures will be needed, which will have fully signed diversion routes in place

We will do all we can to keep disruption to a minimum, but we expect that delays could be severe at peak times, so we are encouraging drivers to plan their journeys to avoid peak times if possible.

Concrete barriers are even stronger than metal ones and significantly reduce the risk of vehicles crossing over from one carriageway to another, improving safety and reducing the duration of incident-related congestion.

They are also virtually maintenance free and will last twice as long as normal metal barriers, with far less need for closures for routine repairs.

Documents

Traffic information

Information about scheduled roadworks and events on our motorways and major roads.

Sign up for updates!

Keep up to date with what's happening on this scheme by signing up to our updates.

Feedback