A27 Fontwell to Arundel resurfacing

We’re carrying out resurfacing and repairs along the A27 between Fontwell and Arundel

Start date January 2024
End date Spring 2024
Cost TBC

Latest updates

  • 26 March 2024

    Resurfacing update

    We’ve finished our planned programme of work. However, as we lost some time due to weather, we’ll need to return to couple of areas to finish our resurfacing over the next few weeks.

    All closures are between 8pm and 6am:

    • Tuesday 2 to Wednesday 3 April: full closure both directions between Fontwell East Roundabout and Ford
    • Thursday 4 to Friday 5 April: westbound between Fontwell East and Fontwell West roundabout
    • Monday 15 to Wednesday 17 April: full closure both directions between Fontwell East Roundabout and Ford
    • Thursday 18, Friday 19 & Monday 22 April: the northern section of the Fontwell East Roundabout will be closed

    For access to properties on the A27, please approach the closure gate and speak to one of the site team. 

    Accessing your property during our work

    We’re carrying out our work in short sections, to maintain access to homes and businesses on the A27.

    Please follow signs for access, or speak to the site team, as the direction you need to approach from may change as we progress. We’ll be posting details of where we’re working here.

    For any properties within the working area, an escort will be provided, please approach the closure point. There could be a short wait while we make it safe for you to pass.

    If you’d like to speak to someone about access, you can call our contact centre on 0300 123 5000 (open 24/7), who will pass your details to the team, or email: info@nationalhighways.co.uk

Project information

Overview

We’re resurfacing and making improvements to the A27 between Fontwell West and the Ford roundabouts.

This will maintain safety and improve the journey for road users, while reducing the need for unplanned closures.

Repairs and maintenance on the A27 are critical for safety reasons. This work is part of our programme of maintenance that keeps our roads safe.

We’ll carry out our work in phases starting from the evening of Monday 15 January. It will take us eight weeks.

This work will take place on weeknights only, between 8pm and 6am, when there’s less traffic on the road.

Work phases

  • Phase one: A27 westbound Fontwell West to Fontwell East roundabouts.
  • Phase two: A27 eastbound Fontwell East to the junction with Long Lane (where it reduces to a single lane in each direction).
  • Phase three: A27 junction with Long Lane to the Ford Roundabout.
  • Phase four: A27 westbound Long Lane junction to Fontwell East Roundabout.
  • Phase five: The Fontwell East Roundabout. 
  • Phase six: A27 eastbound Fontwell West to Fontwell East roundabouts.

Accessing your property during our work

We’re carrying out our work in short sections, to maintain access to homes and businesses on the A27.

Please follow signs for access, or speak to the site team, as the direction you need to approach from may change as we progress. We’ll be posting details of where we’re working, including information about access here.

For any properties within the working area, an escort will be provided, please approach the closure point. There could be a short wait while we make it safe for you to pass.

If you’d like to speak to someone about access, you can call our contact centre on 0300 123 5000 (open 24/7), who will pass your details to the team, or email info@nationalhighways.co.uk.

Documents

Traffic information

Information about scheduled roadworks and events on our motorways and major roads.

Sign up for updates!

Keep up to date with what's happening on this scheme by signing up to our updates.

Feedback