Ash dieback in the North West

Ash dieback is affecting trees on the land we manage. We're taking action to slow its spread and make sure trees along our strategic road network remain safe.

Start date Autumn 2023
End date Spring 2024
Cost TBC

Project information

A590

We will be carrying out tree management works at various locations along the A590 this winter, including:

  • Between M6 junction 36 and Brettargh Holt roundabout in both directions
  • Both sides of the Levens junction
  • Meathop roundabout
  • Lindale Bypass in both directions
  • Newby Bridge to Haverthwaite

Our programme of work starts on Monday 20 November and is scheduled to complete by spring 2024.

Most of the works will be undertaken during the day, however some overnight work may be required.

To maintain safety for the travelling public and our staff, we will work under lane 1 closures wherever safe to do so. In some locations along the A590 we may need to temporarily control the flow of traffic under a two-way traffic light system.

The route will remain open to traffic throughout our work, although minor delays might be experienced at peak hours. We always advise drivers to plan their journeys in advance.

Every effort will be made to ensure the works are completed safely and disruption is kept to a minimum. However, these works may cause small delays to journeys, and we would like to apologise in advance for any inconvenience caused.

We will be carrying out tree works at 12 locations along the M6, between junction 29 (Preston) and junction 38 (Tebay).

Our programme of woodland management starts on Monday 20 November and is scheduled to be complete by spring 2024.

We will typically work at each of the sites on the M6 over a period of five to ten days. We aim to complete most of our work at night, when traffic volumes are at their lowest.

The M6 will remain open throughout, however journeys may be delayed by temporary closures of the hard shoulder, lane 1 and sometimes lane 2 at each location. Lane closures will be in effect for a section of motorway typically a mile or less in length.

Every effort will be made to ensure the works are done safely and disruption is kept to a minimum. However, these works may generate some minor delays to journeys, and we would like to apologise in advance for any inconvenience caused.

We will be carrying out tree management works at various locations along the M61 this winter, including:

• M61 junctions 4 to 5, near St Helens Road – November to December 2023
• M61 junctions 5 to 6, near Chew Moor Lane – December 2023 to February 2024
• M61 between junctions 6 and Rivington Services – November 2023 to March 2024
• M61 northbound from junctions 8 to 9, near Birchen Lane – December 2023
• M61 southbound from its junction with the M6, near Bankhead Lane - February 2024

Our work will focus on removing trees along the route that are suffering from Ash dieback disease that over time will make the trees weaker and unsafe.

We will also be carrying out routine woodland management works to improve the condition of the woodland plots and encourage diversity and fresh growth in the coming years.

Most of the woodland management work will be undertaken during the day, however some overnight work may be required. We’ll be following industry best practice to reduce noise as much as possible.

To maintain safety for the travelling public and our staff, we'll need to work under temporary closures of the hard shoulder, lane 1 and occasionally lane 2. Lane closures will be in effect for a section of motorway typically a mile or less in length.

No work will take place over the Christmas and New Year holiday period, from 19 December 2023 to 3 January 2024, which means lane closures can be removed in full.

The M61 will remain open to traffic throughout our work, although minor delays might be experienced at peak hours. We advise drivers to plan their journeys in advance.

Documents

Traffic information

Information about scheduled roadworks and events on our motorways and major roads.

Sign up for updates!

Keep up to date with what's happening on this scheme by signing up to our updates.

Feedback