M62 Scammonden Bridge parapet replacement

We’re replacing the existing aluminium parapet on Scammonden Bridge with a new steel parapet. We'll start work on 20 April 2026 and expect to finish in January 2027.

Latest updates

  • 19 November 2026

    No further full M62 overnight closures required

    We've now installed all the panels for the new stronger, safer parapets on both the east and west sides. 

    As you'll be aware, while replacing the barriers, we've had to fully close the M62 between junctions 22 (Rockingstone Moss) and 24 (Ainley Top) during weeknights.

    This has been needed to manage the risk of falling debris from height onto the motorway below and keep motorists safe.

    We still have some final works to do on both parapets. These involve lining up, levelling and grouting the parapet base plates, so everything sits level and is firmly fixed in place.

    However, this will not need full closures of the M62. These works will be carried out under later overnight hard shoulder and lane closures, at dates to be confirmed.

    We'll still be able to keep part of the motorway open while we do these works and will not need to divert traffic away from the motorway.

    Closure of B6114 Scammonden Bridge

    We'll still need some overnight closures on the B6114 Scammonden Bridge itself while we continue the final works on the parapets.

    These closures will be installed at the same time as the M62 lane closures, which will take place at dates to be confirmed. 

    By the end of the month, we hope to fully reopen the B6114 Saddleworth Road over the bridge, and just close the bridge at night as and when needed.

    We may need to retain traffic lights and cones for a little longer, but we hope to be able to confirm this shortly. 

    We then plan to have our works complete ahead of Christmas. If there is anything left to complete after this period, we'll need to come back for the occasional shift in the New Year.

    This will involve the odd overnight closure on the bridge as well as lane closures on the M62.

    Where possible, we'll try to keep closures over this bridge to weeknights only; however, there may be times when we'll need to close the bridge overnight at weekends. 

    Please remember that closures can change at short notice. You can check the latest information on our daily closures page. Our travel alerts give details of live incidents on our network.

  • 19 November 2026

    A162 bridge parapet and barrier replacement - from 1 September to end of November 2026 (now extended to February 2027)

    We're replacing parapets and barriers on the A162 north and south bridges over Ferrybridge Roundabout (M62 Junction 33 Interchange), along with essential concrete repairs and bridge joint renewal.

    The current lane 1 closures on the A162 north and southbound, with a temporary barrier and 50mph speed limit in place for safety, are now remaining until February 2027.

    This is to enable the parapets on both sides of both structures to be completed, and quality checks to be undertaken. 

    There will be some overnight (8pm-6am) full closures of the A162 north and southbound between the slip roads for Ferrybridge Roundabout (M62 Junction 33 Interchange).

    A short diversion will be in place for these closures using the exit and entry slip roads. This is to enable the replacement of bridge joints.

    These are expected to take place on some weeknights in November and December 2026 for the south bridge and then during January and February 2027 on the north bridge. The works are heavily weather-dependent. 

    The majority of our concrete repairs from Ferrybridge Roundabout have been completed, although a period of further overnight (8pm-6am) closures of the north quadrant of the roundabout will be required in late January and February 2027 to remove the temporary edge protection and complete one remaining concrete repair. These works are weeknights only and dates will be confirmed. 

    Please see below for the diversion route when the north quadrant of the roundabout is closed:

    A162 roundabout, north side

    Closed overnight (8pm-6am), Monday to Friday.

    Diversion:

    • continue on the A162 northbound to the A645
    • return south on the A162

    Diversion route map for north side 

    Please remember that closures can change at short notice. You can check the latest information on our daily closures page. Our travel alerts give details of live incidents on our network.

  • 09 November 2026

    Panels for parapets now installed

    The new panels for both the eastern and western parapets have now been fully installed.

    We'll now undertake the final touches on the bridge parapets, ensuring everything is secure, level and ready for the years ahead.

    To carry this out safely, we'll need five additional overnight closures on the M62 between junctions 22 and 24 (Ainley Top), in both directions, for finishing works.

    We'll update you as soon as the dates for these closures have been confirmed. 

    Diversions

    During closures, traffic will be signposted to follow the agreed diversion by the:

    • A672
    • A58
    • A646
    • and A629

    We know this has caused severe delays for traffic travelling through this section, as well as overnight disturbance for residents, especially along the A672.

    Once again, we sincerely apologise for the disruption caused.

    We'll work to have this scheme finished as soon as we can.

    B6114 Scammonden Bridge

    The B6114 over the bridge is currently expected to remain closed overnight (Monday to Friday) until the scheme completes in January 2027. However, weekend closures on the bridge deck may occasionally be needed.

    We would like to take this opportunity to thank everyone in the communities affected for their patience and support as we complete these works.

  • 28 September 2026

    Updated closures

    We’re continuing our safety critical work to replace the parapets on Scammonden Bridge over the M62. 

    Our team have made good progress on the west side parapets and is getting ready to begin work on the east side.

    To keep everyone safe while we work above the motorway, we need overnight closures of the M62.

    Thanks to recent progress, we’ve been able to revise the schedule. 

    Closures (9pm–6am)

    • 17 and 18 September - closed eastbound only 
    • 21 to 25 September - open both directions
    • 28 and 29 September - open both directions
    • 30 September to 2 October - closed eastbound only
    • 5 to 9 October - closed both directions
    • 12 to 16 October - closed eastbound only
    • 19 to 23 October - closed in both directions (but may finish sooner depending on progress)
    • 26 to 30 October - closed eastbound only
    • 2 to 6 November - closed in both directions (but may finish sooner depending on progress)

    Please remember that closures can change at short notice. You can find the latest information on our daily closures page or check for current incidents, disruptions and delays. Our travel alerts give details of high priority incidents on our network.

  • 04 September 2026

    M62 eastbound resurfacing scheme

    We're using some of the east and westbound overnight closures for the Scammonden bridge parapet scheme to resurface the M62 eastbound between junctions 22 and 24. 

    We'll be resurfacing overnight, between 1 September and 16 October.

    M62 closures are due every weeknight except for the five weeknights between 21 September and 25 September inclusive, when the M62 will remain open in both directions to allow for local authority works planned on the diversion route.

    Please remember that closures can change at short notice. You can check the latest information on our daily closures page. Our travel alerts give details of live incidents on our network.

  • 18 August 2026

    M62 Scammonden Bridge parapet upgrades - 17 August to end of September 2026

    We're upgrading the parapets on Scammonden Bridge, which carries the B6114 over the M62 between junctions 22 and 23. New steel parapets will keep the bridge safe for the long term.

    17 August to end of September - M62 east and westbound, junctions 22 (Rockingstone Moss) to 24 (Ainley Top)

    Closed overnight (8pm-6am), Monday to Friday only.

    We originally planned to start these closures on 20 July, but postponed them due to the moorland fires near the A628.

    Eastbound diversion:

    • use the A672
    • A58
    • A646
    • and A629

    Westbound diversion will use the same route in reverse.

    M62 junctions 22-24 diversion route map

    M62 will stay open on nights of 24 and 25 August

    This is to allow the full closure of the A628 from 1am Monday 24 to 6am Wednesday 26 August.

    The closures is needed for urgent stabilisation works at Woodhead Cascade.

    August Bank Holiday weekend

    M62 and B6114 over Scammonden Bridge will stay open on the nights of Friday 28 August and Monday 31 August.

    Scammonden Bridge (B6114)

    The B6114 over Scammonden Bridge stays closed every weeknight until the scheme finishes in January 2027. Local diversions are in place.

    Please remember that closures can change at short notice. You can find the latest information on our daily closures page or check for current incidents, disruptions and delays. Our travel alerts give details of high priority incidents on our network.

Project information

Scammonden Bridge carries the B6114 over the M62 between junctions 22 (Rockingstone Moss) and 23 (Outlane). 

The existing aluminium parapets are being replaced with new steel ones to keep the bridge safe for the long term.

Why our programme has changed

Following feedback from the community about the need to maintain access over the bridge, we’ve redesigned our approach. We will now:

  • work on one parapet at a time
  • use both daytime and overnight working (8pm–6am)
  • keep the bridge open during the day, with a single lane and convoy system
  • close the bridge overnight for safety
  • keep reduced speed limits on the B6114 and Ryefield Lane West

Because of this revised approach, restrictions will remain in place until the end of January 2027.

What’s happening and when

You may notice increased activity as we set up our site and traffic management. Preliminary works run until 1 June 2026.

Watch how we're replacing the parapets on M62 Scammonden Bridge.

Main programme

1 June – September 2026

Replace western parapet.

September 2026

Switch lane restrictions for next phase.

September - December 2026

Replace eastern parapet.

January 2027

Lighting and electrical works.

End January 2027

Demobilisation and completion.

M62 overnight closures

To work safely, we’ll close the M62 in both directions between junctions 22 and 24 (Ainley Top) on some weeknights (8pm–6am).

We need to close the M62 in both directions due to the height of the bridge, and to manage the risk of falling debris onto the carriageway as engineers work on the bridge above.

Diversion Route

During these closures, traffic will be diverted by the:

  • A672
  • A58
  • A646
  • and A629

We've worked closely with local authority partners to identify the diversion route that is most suitable for all vehicles, including HGVs.

The diversion route takes into account height and weight restrictions, and avoids roads with low bridges.

We've also taken measures such as installing additional signage to help prevent double parking along the diversion, especially where the route passes through residential areas. 

We'll continue to monitor the situation and work with our partners to take any further action necessary to help traffic flow as smoothly and safely as possible throughout.

Access over Scammonden Bridge (B6114)

The bridge remains open during the day with traffic signals.

Overnight closures

We'll close the B6114 over the bridge overnight (8pm–6am).

Local diversion

You'll be diverted by: 

  • Saddleworth Road (B6114)
  • Stainland Road (B6113)
  • Greetland Road (B6113)
  • Elland Road (B6113)
  • Oldham Road (A672)
  • Ripponden Road (A672)
  • Huddersfield Road (A640)
  • New Hey Road (A640)
  • B6114 Saddleworth Road.

Local diversion map.

Please remember that closures can change at short notice. You can check the latest information on our daily closures. Our travel alerts give details of live incidents on our network.

Documents

Traffic information

Information about scheduled roadworks and events on our motorways and major roads.