M62 Scammonden Bridge parapet replacement

We’re replacing the existing aluminium parapet on Scammonden Bridge with a new steel parapet. We'll start work on 20 April 2026 and expect to finish in January 2027.

Latest updates

  • 21 July 2026

    M62 overnight closures postponed

    Our planned overnight closures of the M62 in both directions between junctions 22 (Rockingstone Moss) and 24 (Ainley Top) are postponed until further notice.

    The A628 is currently closed in both directions between the A616 and A57 while fire services tackle nearby moorland wildfires. It's expected to re-open by Friday 24 July at the earliest.

    While it's closed, we need to keep this stretch of the M62 open as an alternative route.

    We'll update you with new dates as soon as we have them.

  • 13 July 2026

    M62 overnight closures - update

    Phase 1: 

    • every weeknight (8pm-6am) from 20 to 24 July
    • then on the nights of 27, 28 and 29 July

    Phase 2: 

    Every weeknight (8pm-6am) from 12 to 27 August

    If we make enough progress during phase 1, we may move phase 2 to an earlier set of dates.

    We'll update you as soon as possible of any changes to the planned closures.

    These dates represent revisions to previously issued schedules.

    Diversion Route

    During these closures, traffic will be diverted by:

    • the A672
    • A58
    • A646
    • and A629

    Residents may experience increased overnight traffic and associated noise on local roads.

    Future Closures

    Further overnight closures are planned for Autumn 2026.

    Exact dates will be confirmed as the project progresses and may be subject to weather conditions and coordination with other regional works.

    Please remember that closures can change at short notice. You can find the latest information on our daily closures page or check for current incidents, disruptions and delays. Our travel alerts give details of high priority incidents on our network.

Project information

Documents

Traffic information

Information about scheduled roadworks and events on our motorways and major roads.

Sign up for updates!

Keep up to date with what's happening on this scheme by signing up to our updates.

Feedback