A46 package – Cold Ashton roundabout to London Road junction roundabout
We're investing almost £6million to improve the A46 north of Bath between London Road junction roundabout and Cold Ashton roundabout.
How we'll work
To work safely, we’ll mainly use combinations of lane closures and weeknight full closures.
Where needed, we'll put signed diversions in place.
We'll give details of where we're working and the traffic management we're using on this page.
A46 Cold Ashton roundabout and London Road roundabout - 30 November 2026 to 13 January 2027
We’ll be working on the A46 from Monday 30 November to Wednesday 13 January between Cold Ashton roundabout and London Road roundabout.
Closures
The A46 will be closed weeknights (Monday to Friday, 8pm-6am) in both directions.
Monday 30 November to Friday 4 December
We’ll continue resurfacing works and improving road markings at Hartley Bends
Monday 30 November to Wednesday 13 January
We’ll be undertaking geotechnical surveys and installing monitoring devices at Butchers Wood. This will help us to plan for any future works that might be required.
Well signed diversions will be in place for both northbound and southbound traffic by:
- the A420 (Marshfield)
- the A350
- and the A4 (Corsham / Box)
Access will be maintained to properties on the A46 directly within the closure.
Please speak to the site team at the nearest closure point to be escorted through the works.
Please plan ahead and allow extra time for your journeys.
Dates may change at short notice due to poor weather conditions or operational reasons. If we’re unable to complete our work as planned, we may need to continue beyond the dates stated above.
Bath Christmas Market
Please note, our closures will begin later in the evening during the Bath Christmas Market period.
From Monday 30 November until Sunday 13 December, our closure times will be:
- Mondays: 8.30pm-6am
- Tuesdays: 8.30pm-6am
- Wednesdays: 8.30pm-6am
- Thursdays: 9pm-6am
- Fridays: 9pm-6am
- Saturdays: road open as usual
- Sundays: road open as usual
Outside of these dates, closures will be Monday to Friday (8pm-6am).
There will be no planned closures over the festive period from Saturday 19 December to Sunday 3 January.
Please remember that closures can change at short notice. You can check the latest information on our daily closures page. Our travel alerts give details of live incidents on our network.
Project information
The A46 is part of our south western strategic road network - a vital link between Bath and the M4.
It connects the south coast with Bristol, Bath and London, as well as carrying local traffic.
Our improvements will make journeys safer, smoother and more reliable. They'll also reduce the need for future unplanned closures.
Documents
Traffic information
Information about scheduled roadworks and events on our motorways and major roads.Sign up for updates!
Keep up to date with what's happening on this scheme by signing up to our updates.