A14 River Cam Bridge - bridge joints and maintenance

We're carrying out essential maintenance on the River Cam Bridge near Horningsea in Cambridgeshire, due to fire damage, as well as upgrading safety features and resurfacing.

Start date 6 October 2025
End date January 2027
Cost £4 million

Latest updates

  • 28 August 2026

    Planned closures for September to November 2026

    As well as doing repairs on the A14 River Cam Bridge, we’ll also be doing roadside technology upgrades between junctions 33 (Milton Interchange) and 34 (Fen Ditton Junction).

    We start work our main work on Friday 4 September 2026, and expect to finish within 12 weeks.

    We’ll be working overnight between 8pm and 5am on weeknights only, weather permitting. 

    To work safely, we’ll close the A14 in one direction at a time. A 40mph speed limit will remain in place throughout our work for everyone’s safety.

    When the A14 is closed, drivers will need to follow the diversion routes shown in the attached annex.

    Lane closures will also be in place on the A14 eastbound carriageway so we can upgrade roadside technology safely at the same time.

    Closures and Diversions

    Friday 4 September 2026 (1 night) – A14 junction 34 westbound entry slip road and lane 1 closure

    To join the A14 westbound at junction 34:

    • continue south on the B1047.
    • join the A1303 Newmarket Road.
    • follow the A1303 to A14 junction 35, Quy Interchange.
    • join the A14 westbound and continue your journey.

    A14 junction 34 (Fen Ditton Junction) westbound entry slip road diversion

    Monday 7 September to Wednesday 9 September 2026 (3 nights) – A14 junction 33 to 34 eastbound full closure.

    Eastbound diversion:

    • leave the A14 at junction 33.
    • join the A10 northbound.
    • continue to the A142.
    • follow the A142 towards Newmarket.
    • rejoin the A14 eastbound at junction 37.

    A14 eastbound junction 33 (Milton Interchange) to 34 (Fen Ditton Junction) diversion 

    Thursday 10 September to Friday 6 November 2026 (6 weeks) – A14 junctions 34 to 33 westbound full closure

    Westbound diversion:

    • leave the A14 and join the A142 towards Ely
    • join the A10 southbound
    • rejoin the A14 westbound at junction 33.

    A14 westbound junctions 34 (Fen Ditton Junction) to 33 (Milton Interchange) diversion 

    Monday 9 November to Thursday 26 November 2026 (14 shifts) – A14 Junction 33 to 34 eastbound full closure

    Eastbound diversion:

    • leave the A14 at junction 33.
    • join the A10 northbound.
    • continue to the A142.
    • follow the A142 towards Newmarket.
    • rejoin the A14 eastbound at junction 37.

    A14 eastbound junction 33 (Milton Interchange) to 34 (Fen Ditton Junction) diversion 

    Please remember that closures can change at short notice. You can check the latest information on our daily closures page. Our travel alerts give details of live incidents on our network.

  • 17 August 2026

    Repair work below the A14 continues until 28 August 2026

    We're progressing well with the repair works beneath the bridge but the graffiti removal is taking longer than anticipated. 

    We'll continue to work daytime (8am-5pm), Mondays to Fridays only, weather permitting. 

    We’ll work behind the tow paths.

    East and west underside path 

    We're removing graffiti from the bridge supports on both sides of the river.

    West underside path 

    We've completed the repair to the fire - damaged supports on the west side of the bridge.

    Pedestrian and cyclists

    The towpaths will remain open at all times for pedestrians and cyclists. 

    Next phases

    We'll programme the remaining phases of our work for later in the summer, as soon as we've completed the design. 

    We'll return to underneath the A14 in 2027 to install an anti corrosion system to the underside of the bridge. 

    Thanks for your patience while we undertake this essential bridge maintenance.

    Please remember that closures can change at short notice. You can check the latest information on our daily closures page. Our travel alerts give details of live incidents on our network.

  • 11 August 2026

    Repair work continues in August

    We've finished repairing fire-damaged supports on the west side of the bridge.

    However, it's taking us longer than expected to remove graffiti from bridge supports on east and west paths by the river. 

    We'll continue working behind the tow paths Mondays to Fridays daytime (8am-5pm) only, weather permitting. 

    The towpaths will remain open at all times for pedestrians and cyclists. 

    We'll return to perform anti-corrosion work on the underside of the bridge in 2027. 

    Thank you for your patience while we work.

  • 23 June 2026

    Repair work - 6 July to 31 July 2026 

    We've completed our surveys beneath the bridge next to the River Cam. 
     
    We're preparing to start repairs on the west side of the bridge. We'll complete this work in stages

    We'll work daytime (8am-5pm), Mondays to Fridays only, from Monday 6 July to Friday 31 July, weather permitting. 

    We’ll work behind the tow paths.

    East and west underside path  

    We'll remove graffiti from the bridge support on both sides of the river.

    West underside path  

    We'll repair the fire-damaged supports on the west side of the bridge.

    Pedestrian and cyclists

    The towpaths will remain open at all times for pedestrians and cyclists. 

    Next phases

    We'll programme the remaining phases of our work for later in the Summer, as soon as we've completed the design.

    Thanks for your patience while we undertake this essential bridge maintenance.

  • 29 January 2026

    Survey work continues - 9 February to 2 April 2026

    We’re doing survey work underneath the bridge next to the River Cam.

    The survey work is part of a bigger project to refurbish the A14 River Cam Bridge, which is due to start in the summer of 2026.

    We’ll share details of future closures and diversions as soon as they’re confirmed. 

    We'll work weekdays only (8am-5pm, Mondays to Fridays) between Monday 9 February to Thursday 2 April, weather permitting.

    We’ll either be working alongside or on the tow path. 

    For safety, the tow paths under the bridge will have temporary pedestrian diversion routes in place behind the bridge supports while we do this work.

    East underside path 

    We'll be inspecting the underside of the bridge joints with a mobile elevated working platform.

    Tuesday 10 and Wednesday 11 March - West underside path 
    • We'll be inspecting the underside of the bridge joints using a mobile elevated working platform. The temporary footpath will be fenced off after the surveys are completed, and the path will be re-opened after each day

    Lent Bump Boating

    We're not working between 2 and 8 March due to the Lent Bumps boating event taking place on the River Cam

    Summer 2026

    We'll commence the main repair work later in the summer after reviewing the results of the surveys taken during phase one.

  • 06 October 2025

    Survey work from 6 to 8 October 2025

    We’re doing survey work underneath the bridge next to the River Cam.

    The survey work is part of a bigger project to refurbish the A14 River Cam Bridge which is due to start in the new year. We’ll share details of future closures and diversions as soon as they’re confirmed. 

    We'll work weekdays only (8am to 5pm, Mondays to Fridays) between Monday 6 October to Friday 17 October. 

    For safety, the tow paths under the bridge will have temporary pedestrian diversion routes in place behind the bridge supports while we do this work. 

    6 October to 8 October 2025

    East underside path 

    We'll be inspecting the underside of the bridge joints using a mobile elevated working platform. 

    West underside path 

    We'll be inspecting the underside of the bridge joints using a mobile elevated working platform. The temporary footpath will be fenced off after the surveys are completed, and the path will be re-opened.

    Return in 2026

    We'll return in the New Year to complete surveys on the western side and start the main refurbishment works.

Project information

Overview

The River Cam Bridge near Horningsea was built in 1976. It plays a vital role in connecting communities along the A14 Cambridge Northern bypass. 

Over time, the structure has experienced wear and damage. There has also been fire damage.

To ensure the bridge remains safe and reliable for all users, essential maintenance and upgrades are required. 

The work includes repairs on both the bridge deck and underneath, accessed via the A14 and tow paths. 

The project focuses on restoring the fire-damaged bridge support, replacing bridge joints, improving drainage, resurfacing the road, and upgrading safety features. 

The work will ensure the bridge remains safe, reliable, and fit for purpose for all. 

Road users will benefit from a safer and more resilient bridge, and the resurfacing will mean a smoother driving experience. 

These improvements will extend the life of the bridge and reduce the need for future disruptions.  

Documents

Traffic information

Information about scheduled roadworks and events on our motorways and major roads.

Sign up for updates!

Keep up to date with what's happening on this scheme by signing up to our updates.

Feedback