M53 Raby Hall Bridge
We're replacing the central bridge deck of Raby Hall bridge, together with waterproofing and resurfacing of Raby Hall Road.
Latest updates
-
23 November 2026
M53 Raby Hall bridge scheme set to begin
We have upcoming preparatory works on the M53 between junctions 4 and 5 near Raby Mere and Bromborough in the Wirral to prepare for the Raby Hall central deck replacement scheme.
The works start on Saturday 5 December, with lane closures required between junctions 4 and 5 as follows:
- 5 December – northbound full closure (9pm-5am)
- 6 December – southbound full closure (9pm-5am)
- 7 to 16 December – north and southbound lane closures, 24/7
- 7 to 16 December – north and southbound lane closures (9pm-5am)
- 16 December – northbound full closure (9pm-5am)
- 17 December – southbound full closure (9pm-5am)
We'll update the scheme programme in the new year.
To carry out the preparatory works safely, there will be temporary lane closures on the M53 on both north and southbound carriageways for the safety of the workforce and the public.
During the scheme, we'll need to temporarily close Raby Hall Road bridge, to replace the central bridge deck.
A full closure of Raby Hall Road will be required in Spring 2027 for approximately nine months to carry out the demolition and installation of the new central bridge deck.
Two full weekend closures of the M53 between junctions 4 and 5 will also be needed, alongside periods of lane closures and a temporary 50mph speed limit during the construction phase.
More information will follow early in the new year.
Public information event
These works form part of a £50m investment in the M53 corridor. We’re making every effort to reduce the impact on the community and motorists.
The major works for this scheme will begin in the new year, when we plan to host a public information event for the local community to learn more about this scheme.
We'll provide more details of the event, location and date and time later this year.
Scheme milestones
5 December 2026
Enabling works start and a lane one closure for three weeks while the hard shoulder and central reservation are reinforced in readiness for the forthcoming works.
We'll update this page with scheme milestones and project updates in the coming months.
Project information
Documents
Traffic information
Information about scheduled roadworks and events on our motorways and major roads.Sign up for updates!
Keep up to date with what's happening on this scheme by signing up to our updates.