Step 3: Detailed design, grid connection and pre-construction

Grid connection application process

Some sites may require a grid upgrade to deliver EV charging. You can identify your local DNO via the Energy Networks Association (ENA) website. National Grid outlines the detailed process for applying for a grid connection. The grid connection process follows a clear sequence from early enquiry to final switch‑on. This is a summary of what they advise:

1
pre-app icon

Pre-application enquiry

Early discussion with the grid operator to understand requirements and feasibility.

2
formal app icon

Formal application

Submit technical details, expected demand, and pay any application fees.

3
review icon

Review and assessment

The grid operator carries out studies to check grid capacity and safety impacts.

4
connection offer icon

Connection offer

You receive terms, costs, required upgrades, and delivery timescales.

5
contract icon

Contract signing

Accept the offer and formalise responsibilities in a connection agreement.

When going through the application process, remember to engage your DNO early:

  • Have all your documents ready (including a site location plan, a site layout plan and an Energy Networks Association (ENA) EV application form)
  • Plan your upgrade costs