We’ll be carrying out essential repairs and resurfacing on the M11 junction 8, Birchanger Green Roundabout bridges. This will ensure the bridges continue to remain in a safe and serviceable condition.

Start date 10 June 2022
End date September 2022
Cost

Latest updates

  • Upcoming M11/A120 Closures

    Latest Update 1 July 2022

    Due to a change in operational plans we are cancelling the closures that were due to take place over the next two weekends, (Friday 1 July to Monday 4 July and Friday 8 July to Monday 11 July).

    Our work will now resume in September once we have reprogrammed our schedule. We apologise for any inconvenience this may cause.

    Closures and diversions 

    To carry out the work safely, we will need to close the M11 junction 8 bridges. Only one of the bridges will be shut at a time to reduce the impact on local road users and those needing access to Stansted Airport and Birchanger Green Services.  

    North bridge closure (full weekend closures)

    Further dates to be confirmed.

    Diversion when closures are in place

    M11 northbound traffic wishing to travel east will continue on the M11 to junction 9a before re-joining the M11 southbound to exit at junction 8, Birchanger Green Roundabout. (Diagram 2)

    A120 eastbound traffic will be diverted northbound on the M11 towards junction 9a before re-joining the M11 southbound to exit at junction 8, Birchanger Green Roundabout and continue east. (Diagram 2)


    Non-motorway users only

    Eastbound traffic will be diverted from the A120 along the B1383, then turn right to follow Forest Hall Road and Church Road, before travelling south along Bury Lodge Lane and Round Coppice Road to join the A120 at Priory Wood Roundabout. (Diagram 3)

    South bridge closure (full weekend closures)

    Dates:

    • Friday 9 September, 9pm to Monday 12 September, 5am

    Further dates to be confirmed

    Diversion

    M11 southbound traffic wishing to travel west towards Bishop’s Stortford will continue on the M11 to junction 7 before re-joining the M11 northbound to exit at junction 8, Birchanger Green Roundabout. (Diagram 1)

    A120 westbound traffic will be diverted southbound on the M11 towards junction 7 before re-joining the M11 northbound to exit at junction 8, Birchanger Green Roundabout and continue west. (Diagram 1)

    Non-motorway users only

    Westbound traffic will be diverted from Priory Wood Roundabout, along Round Coppice Road, onto Bury Lodge Lane, turn left to follow Church Road and Forest Hall Road to join the B1383 south to the A120 at Bishops Stortford. (Diagram 3)

    Diagram 1

    Diagram 2

    Diagram 3

Project information

Overview

Our works on M11 Junction 8 will replace waterproofing material that has reached its end of life, and is no longer protecting the concrete structure of the bridge, these are essential works to ensure the life-span of the bridges at this junction.

The new protection will ensure a longer maintenance-free period for the bridge, it will remove pot holes from the current surface and replace directional lines and markings on the bridge to ensure drivers can clearly see which lane they need to be in.

Documents

Traffic information

Information about scheduled roadworks and events on our motorways and major roads.

Sign up for updates!

Keep up to date with what's happening on this scheme by signing up to our updates.

Feedback